Converting a Scarborough Side-Split Into a Legal Fourplex

Toronto zoning now allows four units on most residential lots, and Scarborough has thousands of roomy side-splits that look made for it. The catch is the layout itself. Those staggered half-levels make fire separations, exits and plumbing far harder to design than in a bungalow, and that's where most side-split fourplex applications stall at plan review.

By PermitsHub Team9 min read

Key Takeaways

  • Toronto's multiplex zoning permits up to four units in a Scarborough side-split, but the Ontario Building Code requirements for the fire separations, exits and services, not zoning, usually decide whether the conversion works.
  • Because a side-split's floors are offset by roughly half a storey, the fire separation between units becomes a stepped assembly of floors and short walls, and every step has to be continuous and properly rated.
  • The bedroom level over the garage and the lower level beside it are almost always the hardest units to give an independent exit, so plan exterior stairs and door locations before anything else.
  • Lots near the Scarborough Bluffs or a ravine may need TRCA and slope stability review if the work includes additions, new stairs, decks or excavation, which adds time before the building permit can issue.

Side-Split To Four Units

Yes, you can legally convert a Scarborough side-split into four units. Toronto's multiplex zoning permits up to four dwelling units in a house on most residential lots across the city, Scarborough included. The hard part is the building code, not the zoning. A side-split's staggered half-levels mean the floors of one unit don't line up cleanly with the next, so continuous fire separations, independent exits and stacked plumbing are much harder to design than in a bungalow, where every floor sits squarely on top of the one below.

We get this question a lot from owners in Wexford, Dorset Park, Bendale, Agincourt and Cliffcrest, where side-splits from the 1950s through the 1970s line whole streets. They're big houses on decent lots, which is exactly why people look at them for four units. Here's what actually decides whether the plan survives review.

Why a Side-Split Is Not Just a Bungalow With Extra Stairs

Picture the typical Scarborough side-split. On one side you have the main level with the kitchen and living room, and a basement under it. On the other side, half a flight up, you have the bedroom level, which sits over a lower level at or near grade. That lower level usually holds a family room, a laundry or a powder room, and often the attached garage. So you have four levels, but they form two stacks offset by roughly half a storey.

In a bungalow, a basement unit and a main floor unit are separated by one flat floor assembly. You rate the ceiling, deal with the stair, and you're mostly done. In a side-split, any line you draw between units runs through floors, short walls between half-levels, stair openings and sometimes the garage. Plans examiners at Toronto Building look hard at that line, because it's where fire and smoke would travel.

There's also a classification question. Ontario Building Code provisions written for houses with secondary suites are more forgiving than the general rules for multi-unit residential buildings. Once you reach four units, expect to be designing to the fuller requirements. That affects fire resistance ratings, sound separation, alarm systems and exits. How the half-levels count as storeys, including the ones below grade, can also trigger extra requirements such as an interconnected fire alarm system. That's a code analysis question your designer should settle in writing before the layout is fixed.

The Stepped Fire Separation Problem

Every dwelling unit has to be enclosed by a rated fire separation, and that separation has to be continuous. In a side-split it usually ends up stepped like a staircase seen from the side: a horizontal floor assembly under the bedroom level, a vertical wall at the half-level change, then another horizontal assembly over the basement. Each piece needs the right rating, and the joints between them are what examiners and inspectors focus on.

The weak points are predictable. The short wall at the split usually has floor joists from one side bearing on it or framing into it, so getting drywall continuous behind the joist ends is fussy work. Open stair framing between levels has to be enclosed. Ductwork, plumbing and wiring that cross the separation need proper firestopping or rated dampers. And original 1960s construction often has gaps you only find when the ceilings come down.

In a side-split, the fire separation is never one ceiling. It's a staircase of floors and short walls, and the inspector will go looking for the one joint where it breaks.

The attached garage

If the garage stays a garage, the walls and ceiling it shares with any dwelling unit must be a fire separation and sealed against exhaust fumes. If the bedroom level sits over the garage, that ceiling becomes a critical assembly. If you convert the garage into living space or part of a unit, you're into zoning questions about the front wall, the driveway and parking, along with insulating a slab and walls that were never built to be heated.

Getting Four Units Out Safely: Exits

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Exits are where most side-split layouts fail on paper. Each unit needs a way out that meets the code, and you can't route one unit's exit through another unit. Where units share an exit stair or corridor, that shared space must itself be fire separated from the units it serves.

The basement and the main level are usually manageable. The basement often has, or can get, a separate side or rear entrance, and the main level has the front door. The trouble is the other stack. The bedroom level is up half a flight with no door to the outside, and the lower level is often wedged between the garage and the basement stair. Those two units end up competing for the same interior stair.

  • An exterior stair to a new door on the bedroom level is the most common fix, but it needs proper guards, it may need a rear landing, and it has to fit zoning rules for stairs and platforms projecting into side or rear yards.
  • Side yards on many Scarborough side-split lots are narrow on the garage side, which limits where a new exterior stair or entrance can go.
  • Bedrooms in every unit still need windows that meet egress size and sill height rules, which can mean enlarging below-grade openings and digging window wells.
  • Firefighter access matters too: examiners want a clear, reasonable path from the street to each unit entrance, so fences, gates and grading around the side of the house can become drawing issues.

Plumbing, Sound and Services When Nothing Stacks

In a bungalow conversion, the basement kitchen and bathroom drains can usually be tied in near the existing stack. In a side-split, the bedroom level bathroom sits over the lower level or the garage, the main level kitchen sits over the basement, and the two stacks may be well apart. Adding two more kitchens and bathrooms means running new drains across those offset floors, sometimes through the garage ceiling where pipes need freeze protection, and often breaking basement slab to reach the building drain. On older Scarborough lots, check the condition of the clay or cast iron sewer lateral before you plan four units onto it.

Sound separation is the item owners most often forget. Separations between dwelling units in a multi-unit building need a sound transmission rating, typically STC 50, and that applies to the stepped assemblies too. Resilient channel, insulation and added drywall layers eat into ceiling height, which can be tight in the basement and lower level already.

Then there are the utilities. Four units usually means a larger electrical service and separate panels inspected by ESA, a conversation with Toronto Hydro about the service, and possibly a larger water service from the street. Heating also gets harder. Sharing one furnace and duct system across four units is rarely workable once you're designing to multi-unit requirements, so most layouts move to independent systems per unit, which affects where you put mechanical rooms and how ducts cross the separations.

How Bluffs and Ravine Lots Change the Process

If the house is in Cliffcrest, Guildwood, Scarborough Village, West Hill or anywhere close to the top of the Bluffs, check early whether the lot falls within the Toronto and Region Conservation Authority's regulated area or the City's ravine and natural feature protection area. An interior-only conversion may not need TRCA involvement, but most side-split fourplexes aren't interior-only. New exterior stairs, a rear addition, a deck, enlarged window wells or excavation for a walkout can all fall under review.

Where review applies, expect a geotechnical slope stability assessment establishing the stable top of slope and any setback from it, plus a TRCA permit or clearance before the building permit is issued. That adds weeks or months, and it can move the exterior stair you'd planned for the back of the house. Settle it first, not after your drawings are done.

Layouts That Tend to Pass First Review

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

There's no single right answer, but a few patterns come up again and again on side-split files we've worked on in Scarborough.

Four stacked units, one per level

Basement, lower level, main level and bedroom level each become a unit. It's the most intuitive split and the hardest to execute: four sets of separations, the bedroom level exit problem, and a lower level unit that's often too small unless the garage is absorbed into it. It works best on wider houses where the lower level is generous.

Combining levels across the split

Some owners pair the lower level with the basement as one two-level unit, then pair the main level and bedroom level as another, which brings the house to two or three units. A rear addition or an addition over the garage then supplies the rest. Fire separations get simpler because the separation lines follow the natural stacks. The trade-off is the addition itself, which brings zoning setbacks, possible variances and, near the Bluffs, slope review.

Stopping at three

Sometimes the honest answer is that three units in the house fit the layout well and a fourth doesn't. Some owners in that position look at a garden suite in the rear yard instead. How unit counts combine across the house and an accessory building has specific rules, so confirm the current zoning before you commit. Development charges are another reason to check: provincial exemptions cover additional units within limits, and a fourth unit may not be treated the same way. Confirm with the City before you price the project.

What the Scarborough Review Sequence Looks Like

Applications are submitted to Toronto Building and handled by the Scarborough district, based at the Scarborough Civic Centre. The usual order is a zoning review, then the building code review by a plans examiner, then revisions, then the permit. If the plan needs relief from the zoning bylaw, such as an exterior stair in a side yard or an addition that exceeds a setback, that goes to the Committee of Adjustment's Scarborough panel first. That means a public notice, and neighbours do comment on multiplex proposals, often about parking, the number of entrances and rear stairs overlooking their yards.

Expect the first round of examiner comments to focus on the fire separation details at the split, exit paths for the upper and lower units, sound ratings and the code analysis showing how you classified the building. Clear sections through the half-levels save a revision round, because examiners can't approve a stepped separation they can't see. PermitsHub prepares the code analysis, sectional drawings and fire separation details for this kind of conversion, and handles the examiner revisions through to issuance.

During construction, inspections follow the usual stages: framing, plumbing, HVAC, insulation, fire separations before they're covered, and final occupancy for each unit. Plan the drywall schedule around the fire separation inspection. Covering a stepped assembly before the inspector sees it is one of the more expensive mistakes on these jobs.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

ADU / Garden Suite Eligibility

What type of property do you have?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

ADUs

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT