How Long Is a Building Permit Good For in Ontario Before It Expires?

An Ontario building permit has no printed expiry date, but it can still be taken away. If work doesn't seriously start within six months, or stalls for more than a year, the chief building official can revoke it. Here's how that clock works, what the notice looks like, and how to protect a delayed or phased project.

By PermitsHub Team8 min read

Key Takeaways

  • An Ontario building permit has no fixed expiry date, but the chief building official can revoke it if work isn't seriously commenced within six months of issuance or is suspended for more than a year.
  • Your inspection history is the main evidence the building department uses to decide whether a project is active, so book the first inspection as early as the work allows.
  • GTA municipalities send a notice before revoking for inactivity, and a written deferral request with real reasons and a realistic start date is the standard way to protect a delayed or phased project.
  • A revoked permit usually means reapplying under the current Building Code and zoning rules, which can force redesign on projects approved under older rules.

Every Permit Has a Clock

An Ontario building permit has no printed expiry date, but it isn't good forever. Under the Building Code Act, the chief building official can revoke a permit if construction hasn't been seriously commenced within six months of the permit being issued, or if work is substantially suspended or discontinued for more than a year. In practice, Toronto and the other GTA municipalities send a notice before they revoke for either reason, and you can ask for a deferral if your project is delayed for a legitimate reason.

That's the short version. The longer version matters a lot if your financing slipped, your contractor pushed you to spring, or you're building in phases and the second phase is a year or two out.

The two clocks written into the Building Code Act

The revocation powers sit in section 8 of the Building Code Act, 1992, the provincial law every Ontario municipality works under. Toronto, Vaughan, Mississauga and Oakville all apply the same two time-based triggers. Each city's building bylaw only adds its own procedures and fees on top.

  • The start clock: six months after the permit is issued, the chief building official may revoke it if, in their opinion, construction or demolition hasn't been seriously commenced.
  • The stall clock: at any point after work starts, the chief building official may revoke the permit if, in their opinion, the work has been substantially suspended or discontinued for more than one year.

Two words in that law do a lot of work. The first is "may." Revocation is discretionary, not automatic, which is why you'll meet homeowners whose permits sat untouched for years without anything happening. The second is "opinion." The building official decides what counts as a serious start or a real suspension. The Act doesn't give a checklist. Don't plan around a file nobody has pulled yet. Building departments do run reports on inactive permits, and the letters go out in batches.

What "seriously commenced" looks like to a building inspector

From the building department's side, the clearest proof that a project has started is the inspection record. If the permit file shows a booked and completed inspection, nobody is arguing about whether you've begun. If the file is blank six months after issuance, the department has nothing to go on except what you tell them.

Signs that tend to satisfy an examiner: excavation done and a footing inspection booked, demolition under way on a demolition permit, interior strip-out and new framing on a renovation. Signs that don't: a dumpster in the driveway, a fence around the yard, a signed contract sitting in a drawer. We've seen owners point to a delivered lumber package as proof of a start. Material on site shows intent. It doesn't show construction.

The building department measures progress by the inspection history, not your schedule. A file with no inspections booked looks abandoned, even if your crew has been on site for weeks.

Interior renovations are the tricky case. On a basement second unit or a gut renovation, the first required inspection might be framing or rough-in plumbing, which can come weeks into the job. If you're close to the six-month mark and nothing is inspectable yet, keep dated photos, invoices and your contractor's schedule. That's what you'll send if a notice arrives.

How the one-year stall gets triggered

The suspension clock catches projects that started and then stopped. The usual causes are a contractor walking off the job, a builder going under, money running out partway through, or a family situation that pauses everything. A normal winter shutdown on an addition is not a problem on its own, because it rarely runs past a year. A framing inspection in October followed by nothing until the October after next is exactly the gap the inspection history will show.

When the notice of intention to revoke arrives

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Before revoking for inactivity, the building department sends a written notice to the permit holder. The letter says the department intends to revoke and gives you a set period to respond. Read it carefully, because the response window and the options are spelled out there and vary a little by municipality.

The most common way people miss these letters is the address on file. The notice goes to the permit holder's mailing address from the application, which may be a rental you moved out of, your designer's office, or a previous owner if the house changed hands. If you bought a house mid-project, update the permit holder information with the building department right away.

  • If work has actually started, book the next available inspection and send evidence of progress (dated photos, invoices, a contractor letter) before the deadline in the notice.
  • If work hasn't started but will, submit a written deferral request with your reasons and a realistic start date.
  • If the project is dead, you can let the permit be revoked or ask for it to be cancelled, and check whether any part of the permit fee is refundable under the municipal building bylaw.
  • Whatever you choose, respond in writing and keep a copy. Phone calls don't leave a record on the permit file.

Asking for a deferral on a delayed or phased project

The deferral is the tool most homeowners don't know exists. Instead of losing the permit, you ask the chief building official to hold off on revocation for a stated period. Toronto's building bylaw sets out the process, and other GTA municipalities have their own versions. Some charge a fee for a deferral request, so confirm the current fee schedule with your municipality before you file.

Reasons that tend to get a fair hearing are concrete and outside your control: financing approval delayed by the lender, a related Committee of Adjustment application or TRCA permit still in process, a contractor booked into the next season, an insurance claim holding up a rebuild, or a project deliberately planned in phases. "We got busy" is a weaker story. Give a specific restart date and explain what has to happen first.

Phased projects deserve planning before the permit is even issued. If you're doing a main-floor renovation now and an addition or garden suite later, think about whether those belong on one permit or two. One permit covering both phases means the stall clock may start running against you the day phase one wraps up. When we prepare drawings and submissions at PermitsHub, timing the issuance against the owner's real construction schedule is part of the conversation, because a permit picked up too early is a permit that can be lost.

A deferral isn't a blank cheque. If you get one and then miss the new date, a second request is a much harder sell. Ask for the time you actually need, not the time that sounds reasonable.

Revocations that have nothing to do with time

The six-month and one-year clocks get the attention, but the same section of the Act lists other grounds for revocation. Homeowners are often surprised by these because they can come up on an active, busy site.

  • The permit was issued on mistaken, false or incorrect information, such as a survey showing the wrong lot line or an existing basement described as a legal unit when it never was.
  • The permit was issued in error by the department itself.
  • The permit was a conditional permit and the conditions weren't met, for example a required zoning approval that never came through.
  • The permit holder asks in writing for it to be revoked.

The mistaken-information ground is the one we see bite. If the drawings show a setback, a height or an existing condition that turns out to be wrong in the field, an inspector can stop the work and the department can pull the permit. Accurate existing-condition drawings and a current survey prevent most of these.

What a revoked permit actually costs you

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

When a permit is revoked, you don't just apply for the same thing again. A new application is reviewed under the rules in force on the day you reapply. Ontario's 2024 Building Code took effect on January 1, 2025, so a permit issued under the older code and later revoked can come back with new requirements on stairs, energy efficiency or fire separations. Zoning moves too. Toronto has amended its zoning bylaw several times in recent years for multiplexes, garden suites and laneway suites, and a design that cleared zoning two years ago may not clear it today.

There are practical costs on top of that. Your designer has to revise and resubmit drawings, you go back into the examination queue, and you pay new permit fees, with only a partial refund on the old ones if your bylaw allows one. Any work built after the permit was revoked has no inspections behind it, and an inspector reviewing it under a new permit can ask you to open up walls or ceilings to see what's inside.

Losing a permit costs more than the fee. You go back to the start of the queue under today's code and today's zoning, with drawings that may no longer pass.

The permit you forgot to close

The opposite problem is just as common: work that finished years ago on a permit nobody ever closed. Without a final inspection, the permit stays open on the municipal record. It may also eventually be flagged as inactive. Buyers' lawyers search permit history, lenders and insurers ask about it, and an open permit on a finished renovation can hold up a closing.

We run into this constantly in the older housing stock of North York and Etobicoke, where a 1990s deck or basement permit from a previous owner is still sitting open. Closing it usually means booking the outstanding inspections and sometimes exposing work so the inspector can see it. PermitsHub pulls permit histories and coordinates those close-out inspections. The earlier you start, the less likely it collides with a sale date.

The simplest habit: when your permit is issued, write two dates in your calendar, six months out and one year after your last inspection. If either date is getting close and the site is quiet, deal with it before the department sends you a letter.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Permits 101

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT