Using a Toronto Preliminary Project Review to Lock Your Variance List
Miss one variance at the Committee of Adjustment and your permit can stall until you go back for a second hearing. A Preliminary Project Review gets a Toronto zoning examiner to check your drawings against By-law 569-2013, and any legacy by-law that still applies, before you file. The result is only as reliable as the drawings you hand in, so here is what to send and what to freeze.
Key Takeaways
- A Preliminary Project Review produces a list of zoning non-compliances written by a Toronto Building zoning examiner, and that list is the closest thing you can get to an official variance list before you file at the Committee of Adjustment.
- The review only checks what is on the drawings, so a package without grade points, area calculations, landscaping numbers and full elevations will return an incomplete list that looks complete.
- If your permit drawings later reveal a variance the Committee never approved, the usual fix is a new application and another hearing, which can push your build back by months.
- Once the review comes back, freeze the design, because any change to height, depth, footprint or grade can create a new non-compliance that was never reviewed.
Lock Your Variance List
A Toronto Preliminary Project Review (PPR) is a paid zoning check by a Toronto Building zoning examiner. They read your proposed drawings against Zoning By-law 569-2013, and against the former municipal by-law where it still applies to your lot, and send back a written list of every provision the design doesn't meet. That list becomes your variance list for the Committee of Adjustment. If the drawings you submit are complete and final, the list is reliable. If they're thin, the examiner can only review what's there, and the variances they couldn't see tend to show up later at building permit stage.
What the examiner actually sends back
The result arrives as a zoning notice. It cites each section of the by-law your design doesn't meet, states what the by-law permits, and states what you're proposing. A typical rear addition on a detached house in a residential zone might come back with four or five items: building depth, floor space index, side yard setback, main wall height and rear yard soft landscaping. Each line is written in the same language the Committee uses on its public notice, which is the real value. Your planner or designer doesn't have to guess at the wording or the numbers.
What you don't get is an opinion on whether the variances will be approved. The examiner isn't a planner and doesn't weigh the four tests under the Planning Act. Their job is narrower and more mechanical: does this drawing comply, yes or no, and if no, by how much.
Why one missed variance can cost you a second hearing
The Committee of Adjustment can only approve the variances that were publicly noticed. Neighbours get a notice listing exactly what you're asking for, and the decision approves exactly that list. When you later apply for the building permit, a different examiner reviews the permit drawings. If they find a non-compliance that wasn't on the approved list, the permit can't be issued for that design. Your options at that point are all slow. You can redesign to remove the problem, or you can file a fresh minor variance application, wait for a new hearing date, and sit through the appeal period again.
We see this most often with items that feel trivial to the homeowner. A rear deck that sits a little too high above grade. An eave that projects too far into a side yard. A front walkway that eats into the required soft landscaping. None of these change how the house looks from the street, but each one is a separate provision in the by-law, and each needs its own variance.
The variance that sinks a schedule is almost never the big one. It's the deck platform or the eave projection nobody drew carefully because it didn't seem like zoning.
There is some flexibility at the hearing itself. The Committee can amend an application, and if it considers a change minor it may proceed without sending out a new notice. Adding a variance that neighbours never heard about is a different matter, and panels often defer instead so the change can be re-circulated. You shouldn't plan around getting lucky on the day. Confirm the current rules with the Committee of Adjustment office, but the safe assumption is that your noticed list is your final list.
The drawing package that produces a reliable list
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
Most incomplete variance lists trace back to an incomplete submission, not a careless examiner. If a dimension isn't shown, the examiner may flag it as information required, or may simply not be able to assess it. Either way you end up with a list that has holes. Here is what we include before we submit a PPR for a client:
- A current survey by an Ontario Land Surveyor showing lot lines, existing structures, trees and spot elevations. Old surveys from a previous sale often miss sheds, fences and grade changes.
- A site plan with every setback dimensioned to the closest point of each wall, plus projections such as eaves, bay windows, porches, stairs and decks.
- Floor plans for every level, including the basement, with gross floor area calculated room by room so the examiner can check floor space index.
- All four elevations with established grade, the height of the main walls, the overall building height and the first floor height clearly marked.
- At least one building section showing ceiling heights, roof structure and how height is measured from established grade.
- Landscaping calculations for the front yard and rear yard, separating soft landscaping from hard surfaces like walkways, patios and driveways.
- Deck, platform and stair details showing height above grade and distance to lot lines.
- A statistics table summarizing lot area, coverage, gross floor area, building depth, building length and parking.
Established grade is where most lists go wrong
Under By-law 569-2013, height for most residential buildings is measured from established grade, which is generally based on elevations at the front lot line rather than the ground right next to the house. On a sloping lot, the difference between those two numbers can turn a compliant addition into one that needs a height variance, or the reverse. If your elevations show height from the finished floor or from the ground at the back of the house, the examiner's height result means very little. Put the grade points from the survey on the drawings and show the calculation.
Show the existing house, not only the new part
Homeowners planning a rear addition often want to submit only the new work. The examiner needs the whole building, because coverage, floor space index and building depth are measured on the full structure. An existing side yard that has never complied can also become a variance once you extend that wall backward, since the new portion has to meet today's rules.
When a legacy by-law is still part of the review
By-law 569-2013 covers most of the city, but not every property, and not always cleanly. Some lots are still governed by a former municipal by-law, such as 438-86 in the old City of Toronto or the North York, Etobicoke, Scarborough, York or East York by-laws. Others are subject to transition provisions or site-specific exceptions that mean an examiner has to check more than one document. When that happens, your zoning notice can list variances under two by-laws, sometimes with different numbers for what looks like the same issue, because each by-law measures height, depth or floor area its own way.
This is one of the strongest reasons to get a PPR rather than relying on a designer's own zoning analysis. Working across North York and East York, we regularly see older bungalows and semis where the applicable by-law, a site-specific exception or a past Committee decision changes the answer. Your Committee application has to carry every variance the examiner identified under every by-law that applies. Copy the notice exactly, section numbers included.
Freezing the design between the review and the hearing
A PPR checks one set of drawings on one date. The moment the design changes, the list may no longer match. This is where good projects slip. The client meets a contractor who suggests pushing the kitchen back another metre. The architect raises the ceiling to fit a deeper beam. The landscaper adds a patio. Each change is reasonable, and each can trigger a provision the original review never touched.
Our rule is simple. After the PPR comes back, the zoning-relevant envelope is frozen: footprint, depth, height, wall heights, floor area, setbacks, decks and landscaped areas. Interior layouts can still move. If something in the envelope has to change, the drawings go back for another review before the Committee application is filed. Doing that costs a few weeks. Skipping it can cost a season.
The same discipline applies after the hearing. The approved variances are tied to the drawings filed with the Committee, so the permit drawings need to match them. PermitsHub prepares the PPR set and the permit set from the same model for exactly this reason. Two separately drafted sets are how a 7.0 metre wall on one drawing becomes 7.3 metres on the other.
Preliminary Project Review or zoning certificate: which one fits
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
People searching before they apply often see both terms and assume they're interchangeable. They're not. A zoning certificate is generally used to confirm that a proposal complies with zoning, for example for a project that doesn't need a building permit but still has to show compliance. It is most useful when you expect a clean result. A Preliminary Project Review is built for the situation where you expect non-compliance and need it itemized. If you already know the addition is too deep or too tall, the PPR is the tool that turns that suspicion into a precise list the Committee can act on.
Some owners skip both and file the building permit first, using the zoning notice issued during permit review as their variance list. That works, and on some projects it's faster, because you're producing the permit drawings anyway. The tradeoff is that you've done the full permit drawing set before knowing whether the Committee will approve the design. If the panel cuts your depth or height, those drawings need rework. Toronto Building and the Committee office can tell you what kind of zoning review they currently expect with an application. Check before you file, because the Committee generally wants some form of examiner review on the file, and filing without one usually means formally accepting the risk that the list is incomplete.
Turning the notice into a Committee application
Once you have a clean zoning notice and a frozen design, the application itself is mostly assembly. The variance list from the notice goes into the application form word for word. The same drawings the examiner reviewed go into the Committee package. Your planning rationale, or cover letter on a simpler file, explains why each variance is minor and fits the neighbourhood, ideally with examples of similar approvals on nearby streets. If you want help assembling that package, PermitsHub can review your PPR result and drawings for free and flag anything that looks under-documented before you file.
The point of all this is that the variance list should be the most boring part of your hearing. Neighbours may object, city planning staff may comment, and the panel may ask for conditions. None of that should involve discovering that the list itself was wrong.