Bench Footing or Underpinning to Lower a Don Mills Bungalow Basement?

Most 1950s bungalows in Don Mills and along Bayview have basements you can barely stand up in. You can lower the floor with a bench footing or with full underpinning. The right choice depends on how much floor area you can give up, what the till and clay under your house are doing, and whether a second storey or a teardown is on the horizon.

By PermitsHub Team9 min read

Key Takeaways

  • A bench footing lowers the floor without digging under your existing footings, but the concrete bench eats into the perimeter of the room, and the deeper you go the wider it gets.
  • Underpinning keeps your full floor area and gives you new, deeper footings, but Toronto Building's North York district office will want engineered drawings that show the excavation sequence, pin dimensions and temporary support.
  • If a second-storey addition is realistic in the next decade, underpinning designed for the future load usually makes more sense than a bench, which adds no bearing capacity to the old footings.
  • Glacial till and clay under Don Mills lots hold water and can hide boulders, so drainage, sump and backwater valve details belong in the permit set from day one.

Lowering The Bungalow Floor

If you need only a modest drop in floor height and can live with a concrete ledge around the edge of the room, a bench footing is usually the simpler and cheaper way to lower a shallow Don Mills or Bayview bungalow basement. If you want full headroom, the whole floor area, or a foundation that can carry a second storey later, underpinning is the better choice. Both need a building permit from Toronto Building. Underpinning also needs engineered sequencing drawings that the North York district office will review closely before anyone picks up a shovel.

That's the short version. The longer version depends on your house, your soil and what you plan to do with the property over the next ten years. Here's how we think it through with homeowners in this part of North York.

Why Don Mills and Bayview basements sit so low

Don Mills was built quickly in the 1950s as a planned community, and the builders weren't thinking about basement apartments or home gyms. Basements held the furnace, the laundry tubs and a coal or storage room. Clear heights under the joists commonly land somewhere around six and a half feet, and once you account for ductwork and a dropped beam you're often well under seven. The bungalows along Bayview, through Bayview Village and down toward York Mills, tell a similar story, with some split-levels thrown in that have even less height in the lower section.

The footings under these houses are typically shallow, sized for a single storey, and sit on glacial till or clay. Till is dense and generally a decent bearing material, but it can be studded with cobbles and the occasional boulder that stops a hand-dug pin cold. Clay holds water. Put those two together and you get basements that are structurally fine as they are but that resist being dug deeper without a plan.

How a bench footing works, and the floor area it costs you

A bench footing leaves the existing footing exactly where it is. The crew digs out the floor in the middle of the basement, but stops short of the walls and leaves a sloped or stepped wedge of soil that keeps supporting the original footing. That wedge is then encased in a concrete bench that runs around the inside perimeter of the foundation. The new slab is poured lower, inside the bench.

The catch is geometry. The soil under a footing spreads its load outward on an angle, so the deeper you lower the floor, the farther the bench has to project into the room to keep that zone undisturbed. A small drop gives you a narrow ledge you can turn into a built-in shelf or a window seat. A bigger drop gives you a bench wide enough to wreck a bedroom layout, push stairs out of position and make a code-compliant egress window awkward to reach.

In a typical Don Mills bungalow footprint, losing a strip around the full perimeter adds up quickly. It's the reason bench footings work best when the goal is a recreation room or storage area with better headroom, not a layout that has to fit bedrooms, a bathroom and a kitchen.

A bench footing saves you from digging under the house, but you pay for it in square footage forever. Measure the bench before you fall in love with the floor plan.

How underpinning works under a 1950s bungalow

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Underpinning extends the foundation downward. The crew digs small sections under the existing footing one at a time, pours new concrete footing and wall below it, lets it cure, then moves on. The sections are done in a staggered sequence so that no two adjacent pieces of the old footing are unsupported at the same time. When every section is complete, the house is sitting on new, deeper footings and the full basement floor can be lowered.

You keep every square foot of floor area, and the new footings can be designed for more load than the originals. The trade-off is risk and process. Digging under a house that's still standing is the kind of work where sequence, pin width and cure time matter. In till, the crew may hit a boulder halfway through a pin and need the engineer back on site to decide what to do. In wet clay, open pins can soften or slough if they sit too long or if it rains hard.

The drawings each method needs at the North York district office

Lowering a basement floor is structural work, so either approach needs a building permit through Toronto Building. For a Don Mills or Bayview address, the file is handled by the North York district office at the North York Civic Centre. The level of detail the examiner expects is very different between the two methods.

What a bench footing submission usually includes

  • Existing and proposed basement floor plans showing the bench width around the full perimeter and the new usable floor area
  • A building section through the foundation showing the original footing, the undisturbed soil zone and the new slab elevation
  • A structural detail for the bench, typically sealed by an engineer, with concrete, reinforcing and dowel information
  • Drainage details: weeping tile at the new level, sump pit location and the connection to the storm or discharge point
  • Plumbing changes if floor drains, the main drain or a backwater valve are being relocated or added

What an underpinning submission usually includes

  • Engineer-sealed underpinning plan showing every pin, numbered in the order it will be excavated and poured
  • Typical pin section with dimensions, depth below the existing footing, reinforcing and the dry-pack or grout detail at the interface
  • Notes on maximum pin width, minimum cure time between adjacent pins and what happens if unsuitable soil or an obstruction is found
  • Temporary support for any interior beam, posts or point loads that need to be carried while the floor is excavated
  • New footing design for interior columns, plus the slab, vapour barrier, insulation, drainage and sump details
  • A requirement for engineer field reviews during construction, with reports the inspector can ask to see

The sequencing drawing is where incomplete applications stall. Examiners send back sets that show a single typical pin with no layout, sets that don't address the centre beam and posts, and sets where the underpinning stops at a stair or a chimney without explaining what happens there. A 1950s chimney base sitting on its own footing in the middle of the wall is a classic gap. At PermitsHub we prepare the plans, sections and coordination with the structural engineer so the sequencing sheet answers those questions before the examiner has to ask.

What examiners, inspectors and neighbours flag on these jobs

On the review side, the common comments are about ceiling height and use. If the lowered basement is going to become a secondary suite, the Ontario Building Code sets minimum ceiling heights and egress rules for that suite, and the examiner will check that the drawings actually achieve them once the new slab, insulation and finished floor are in. Lowering a floor and still ending up short because nobody counted the subfloor and ductwork is a frustrating outcome. Confirm the exact height requirement that applies to your project with Toronto Building or have it checked during a drawing review, because it depends on whether you're creating a suite and how the code treats existing houses.

On site, inspectors want to see excavations and reinforcing before concrete goes in. With underpinning, expect them to ask whether the engineer has been out and whether the sequence on the drawings is the sequence being followed. Crews that open three pins side by side to save time are the reason these drawings exist.

Neighbours are a smaller issue in Don Mills than in older parts of the city, since most houses are detached with side yards. Still, a side yard can be narrow, and underpinning a wall near the lot line puts excavation close to a neighbour's foundation and fence. A short heads-up conversation and photos of the neighbour's foundation before work starts are cheap insurance. If your lot backs onto one of the ravines in the Don watershed, check early whether it falls inside a TRCA regulated area or the City's ravine protection bylaw, because exterior excavation or waterproofing there can trigger a separate approval.

Choosing with your next ten years in mind

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

The method that wins on today's budget isn't always the one that makes sense for the property. Plenty of Don Mills and Bayview owners are lowering the basement as step one of a larger plan, and that plan should drive the decision.

  • Second-storey addition likely: lean toward underpinning, and ask the engineer to design the new footings for the future load now. A bench footing adds no bearing capacity to the original footings, so an addition would likely mean reopening the basement anyway.
  • Teardown and rebuild within a few years: think hard about doing either. Money spent on a deeper basement under a house you plan to demolish rarely survives the rebuild.
  • Rec room or storage, no suite, no addition: a bench footing with a modest drop is often the sensible call.
  • Legal secondary suite: underpinning is usually easier, because the full floor area makes bedroom sizes, a bathroom and egress far simpler to lay out.
  • Very wet lot or a history of flooding: either way, budget the design effort for drainage, a sump and a backwater valve, and look at whether the City's basement flooding protection program applies to you.

Cost follows the same logic. Underpinning involves more excavation, more concrete, more engineering and a slower schedule, so it runs meaningfully higher than a bench footing on the same house. The biggest cost swings tend to come from soil surprises, the number of interior columns that need new footings, and whether the plumbing has to be dropped to the new floor level. Get the soil and plumbing questions answered in design, not after the first pin is open.

We've worked on a lot of these bungalows between Lawrence and York Mills, and the projects that go smoothly are the ones where the owner decided early what the house would look like in ten years. If you're still weighing it, PermitsHub can review your existing basement, the zoning picture for a future addition and the structural options before you commit to drawings for either method.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Basements

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT