How Much Window Glass Does a Bedroom Need Under the Ontario Building Code?

A bedroom window can be big enough to climb out of and still be too small for the Ontario Building Code. The natural light rule measures glass against floor area, and it's a completely separate test from egress. In GTA basements, it's the one that quietly fails permit drawings.

By PermitsHub Team9 min read

Key Takeaways

  • Under Part 9 of the Ontario Building Code, a bedroom needs unobstructed glazing equal to about 5 percent of its floor area, and living and dining rooms need about 10 percent. Confirm the current table with your municipality, because the code was reissued in 2024.
  • The glazing test counts glass only, not the rough opening or the frame, so a window that meets the egress opening minimum can still come up short on light in a larger bedroom.
  • Basement bedrooms most often fail on glazing because of three things: undersized existing openings, sill heights that can't drop without a deeper window well, and side walls too close to the lot line for more unprotected openings.
  • The cheapest fix is usually on paper: shrink or reshape the bedroom so its floor area matches the glass you can realistically get, before any excavation is priced.

Glass Versus Floor Area

Under the Ontario Building Code, a bedroom needs window glazing equal to roughly 5 percent of the floor area it serves, and living rooms and dining rooms need roughly 10 percent. That's the natural light rule in Section 9.7 of Part 9. It's a separate requirement from the egress window rule, which is about the size of the openable part of the window (at least 0.35 square metres of clear opening, with no dimension under 380 mm). One window can do both jobs, but it has to pass both tests independently. In basements, the light test is usually the one that fails.

Two window tests that happen to share one opening

Homeowners usually hear about egress first, because it's the life-safety rule everyone talks about. Egress asks one question: can a person get out through this window in a fire? The examiner looks at the clear opening when the sash is fully open, and the minimum width and height of that opening. The glass doesn't matter much for egress. A casement with a narrow frame and a wide swing can pass easily.

The natural light rule asks a different question: is there enough glass in this room for daylight? It ignores how the window opens. A fixed picture window with no operable sash at all can satisfy the light rule completely and fail egress outright. A casement that swings wide open can satisfy egress and still fall short on light if the room is big. The examiner checks each test on its own line of the review.

Egress measures the hole you can climb through. Natural light measures the glass you can see through. Plan examiners check both, and passing one tells you nothing about the other.

The Ontario Building Code was reissued in 2024 and took effect at the start of 2025, so article numbers in older guides may have shifted. The approach to minimum glass area in houses hasn't fundamentally changed, but check the current table with your building department before you finalize window sizes.

Running the glazing math on a typical basement bedroom

Start with the floor area of the room, then take the percentage. A basement bedroom measuring 3.0 m by 3.6 m is 10.8 square metres. At 5 percent, it needs about 0.54 square metres of glass. Now look at what's actually in the wall.

The original basement windows in a lot of 1950s and 1960s GTA houses are short hoppers or sliders, often around 800 mm wide and 400 mm high at the rough opening. Once you subtract the frame and sash, the visible glass in one of those can be well under half the 0.54 you need. Even a new egress casement sized right at the code minimum for opening area may carry only a little over 0.4 square metres of glass, because frames eat into the area. That window gets you out of the room. It doesn't light the room, at least not by the code's measure.

Notice what counts. The code number is glazed area, which means glass, not rough opening and not frame. Contractors size windows by rough opening, so the drawings say one thing and the glass works out to something noticeably smaller. That gap is where we see examiner comments land most often.

  • Measure the room's finished floor area, not the area of the footprint before framing.
  • Apply the right percentage: about 5 percent for bedrooms and other finished rooms, about 10 percent for living and dining rooms.
  • Get the actual glass dimensions from the window manufacturer's spec sheet, not the rough opening.
  • Add up the glass in every window serving that room. Two smaller windows can meet the number together.
  • Check the egress opening separately on at least one window in each bedroom.

Why basement bedrooms pass egress and still fail on light

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Most failures come down to three site conditions working against each other. You usually can't solve one without running into the next.

The existing opening is too small and too high

Basement windows in post-war bungalows and side-splits sit high in the foundation wall, close to grade, with the top of the opening tight under the sill plate or rim joist. You can't make the window taller upward without touching structure above. The only direction to grow is down and sideways. Going wider means cutting more foundation wall and adding a proper lintel. Going down means cutting below grade.

Lowering the sill drags the window well with it

Once the window extends below grade, you need a window well, and the well has to provide clear space in front of the window for egress (the code calls for clearance in front of the window when it opens into a well, and casement sashes can't block that space). A deeper well means more excavation, a drain at the bottom tied into the weeping tile or a drywell, and sometimes a guard at the top. On lots with a driveway right beside the house, or a gas meter on that wall, there's simply no room for the well you'd need. The window stays small, and the bedroom fails on glass even though a code-minimum egress unit fits.

Side walls close to the lot line limit how much glass you can add

This is the one homeowners never see coming. Part 9 limits the area of unprotected openings (windows, basically) in any wall that faces a property line, based on the limiting distance to that line. On narrow Toronto lots in East York, the Danforth, or older parts of Etobicoke, side yards are often around a metre or less. At distances that tight, the code allows very little glazing on that wall, and in some cases effectively none without fire-rated assemblies. The portion of a basement wall that sits above grade counts as part of that exposing face. So the side-wall bedroom you planned can be capped on glass by fire separation rules before the light rule even comes into play.

We've reviewed a lot of Scarborough bungalow basements where the plan put two bedrooms along the side wall facing the neighbour's driveway, because that's where the old windows were. On paper the egress casements fit. Once limiting distance and the glazing percentage were both run, one of those rooms couldn't be a bedroom at that size.

The side wall is where basement bedroom plans go to die. Check limiting distance before you assume a window can get bigger.

Which rooms need glass, and which can rely on lighting

Not every room in a basement suite carries the glazing requirement. The table in Section 9.7 sorts rooms by use. Bedrooms and other finished rooms take the lower percentage. Living rooms and dining rooms take the higher one. Kitchens, bathrooms, laundry rooms and similar spaces can generally rely on electric lighting instead of windows. Unfinished basement space needs only a token amount of glass.

The living room is the expensive one. At 10 percent, a 4 m by 6 m basement living area needs about 2.4 square metres of glass, which is a lot of glazing to fit into a foundation wall. Designers handle this in a few ways: putting the living area against the rear wall where a walkout or a wide window well is possible, keeping the living room modest in size, or opening it to a kitchen in a way the examiner accepts as one combined space. Whether a combined space can be treated as a single room depends on how open the connection is, so confirm the approach with the plan examiner before you build the layout around it.

Dens and offices are a grey area people try to exploit. Labelling a windowless room as a den or storage doesn't fool an examiner if it has a closet, a door, and the dimensions of a bedroom. Inspectors notice when a den gets a bed in it at final, and in a rental suite that becomes a property standards and fire safety problem later.

Fixes that work, and ones examiners send back

When a bedroom comes up short on glass, the options run from cheap and fast to structural and slow. Try them roughly in this order.

  • Shrink the bedroom. Moving one partition to cut the floor area brings the required glass down in proportion. This is the most common fix and it costs nothing in excavation.
  • Add a second window to the same room on a different wall, ideally the front or rear where limiting distance isn't a constraint.
  • Swap the window type. A slimmer-frame casement or a unit with more glass per rough opening can close a small gap without cutting more wall.
  • Widen the opening rather than deepening it, where the foundation and the lintel design allow, to avoid a deeper well.
  • Lower the sill and build a proper window well, accepting the excavation, drainage and possible structural work that comes with it.
  • Relocate the bedroom to a wall with better exposure and turn the dark room into a bathroom, laundry or storage space that doesn't need glazing.

What doesn't work: counting the glass in a door to a furnace room, borrowing light through an interior window from a hallway, or relying on light wells that are really just decorative. Glazing in an exterior door serving the room may count, but confirm that with your examiner on the specific design. Skylights aren't an option under a floor above. And arguing that a room gets good light from a sunny well won't change the math. The code counts glass area, not how bright the room feels.

For existing houses, Part 11 of the code sets out compliance alternatives for some renovation scenarios, and secondary suites in existing houses have their own set of provisions. Whether any of those apply to window area in your particular project is a question for the plan examiner, not something to assume. A written answer before submission saves a revision cycle.

How to show natural light compliance on permit drawings

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Most glazing comments come back because the drawings didn't show the math, not because the design was wrong. Examiners in Toronto, Mississauga and York Region all want to see the same things: room names and floor areas on the plan, window sizes tagged with a schedule, and a calculation showing required glazing against provided glazing for each room. Where a wall faces a side lot line, the spatial separation calculation for that face should sit on the same sheet so the examiner can see both limits together.

When PermitsHub prepares basement suite drawings, we run the glazing table and the limiting distance check before the layout is finalized, not after, because moving a wall on paper is free and moving it after framing isn't. If a bedroom can't hit its number, we'd rather tell you at the zoning and code review stage than read it in a refusal notice. Inspectors will also check that the windows installed match the schedule, so a last-minute switch to a cheaper unit with a heavier frame can turn a passing room into a failing one at framing inspection. If you're mid-project and an examiner comment has flagged glazing or egress, our team can rework the layout and window schedule and handle the resubmission.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Basements

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT