Toronto Building Permit Status Online and What Each Status Means

Toronto's online permit lookup tells you more than whether your permit is issued. It shows which reviewer is holding your file, whether an Examiner's Notice is waiting on you, and which inspections are still open. Here's how to read every line, and what each status means you should do next.

By PermitsHub Team9 min read

Key Takeaways

  • You can check any Toronto building permit status online by searching the property address or the application number on the City's permit status search at toronto.ca, and you don't need an account.
  • An Examiner's Notice means a reviewer found deficiencies and your file is paused until you or your designer respond, so the clock is now on your side of the table, not the City's.
  • Zoning and building review appear as separate lines because they are separate checks against different rules, and a pass on one tells you nothing about the other.
  • A permit marked issued can still show outstanding inspections for years, and an open permit on title is one of the most common reasons a buyer's lawyer raises a requisition before closing.

Reading Your Permit Status

To check a Toronto building permit status online, go to the City of Toronto's building permit status search on toronto.ca and enter either the property address or the application number. You'll see every permit and application tied to that address, the current status of each, which review disciplines (zoning, building, plumbing, HVAC and so on) have signed off, and which inspections have passed or are still outstanding. The status tells you who has the file right now: if it says an Examiner's Notice has been issued, the City is waiting on you; if it says under review, you're waiting on the City; if it says issued but inspections are open, the permit isn't finished until the final inspection passes.

Finding Your File: Address Search vs Application Number

The address search is the easier way in, but it can also be the most confusing. On an older house in East York or the Annex you might see a dozen records going back decades: a deck permit from the nineties, a plumbing permit for a basement bathroom, a demolition permit nobody remembers. Each one is a separate folder with its own status. Before you panic about something that says open, check the date and the description.

The application number is more precise. Toronto numbers start with a two-digit year, followed by a sequence number and a short code for the permit type, such as BLD for building, PLB for plumbing, HVA for heating and ventilation, DRN for drains and DEM for demolition. One renovation can generate several of these folders. A basement second suite, for example, often has a building folder plus a separate plumbing folder and sometimes an HVAC folder. They move at different speeds, so one being issued doesn't mean the others are.

  • Search by address when you're buying a house, checking a previous owner's work, or you've lost your paperwork.
  • Search by application number when you're tracking your own active file and want to see only that folder.
  • If the address doesn't return anything, try the municipal address exactly as it appears on your tax bill, including any unit suffix or the corner-lot address you didn't think of.
  • Records from before the City moved to electronic tracking may not show online at all, and those need a formal building records request.

The Application Statuses, in the Order You'll Usually See Them

The exact wording on the screen has changed over the years and can differ slightly between permit types, so treat these as the stages rather than a word-for-word list. What matters is reading which side of the counter the file is on.

Application received or intake

The City has your submission but hasn't confirmed it's complete. Under the Ontario Building Code, the statutory review clock for a house only starts once the application is deemed complete, with all required drawings, forms and applicable law approvals attached. If the file sits here a long time, something is often missing, like a site plan without setbacks dimensioned or a missing designer's BCIN on the schedule.

Under review

Examiners are working on it. This is where the separate discipline lines matter, which we'll get to below. For a house, the Code sets a short decision window once the application is complete (commonly cited as 10 business days for houses), but that's a window for a decision, and a decision can be an Examiner's Notice rather than a permit.

Examiner's Notice issued or not ready for issuance

The review found problems. The file is now waiting on you. More on this one shortly, because it's the status people misread most.

Response received

You've resubmitted revised drawings and the examiner has them. Don't expect the same quick turnaround as the first review. Resubmissions go back into the reviewer's queue, and if your response only fixed some of the items, you'll get a second notice.

Ready for issuance

Every discipline has signed off. What's usually left is paying remaining fees or charges, such as development charges where they apply, or posting a deposit. People sometimes assume the City will just mail the permit. It won't until those items are cleared.

Permit issued, then inspections, then closed

Issued means you can legally start work. The folder then sits in an inspection stage while construction happens. Closed (sometimes shown as completed) means the final inspection passed and the file is done. Other statuses you might see include refused, cancelled, and revoked, each of which means that application is no longer live.

What an Examiner's Notice Actually Means

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

An Examiner's Notice is a list of deficiencies. It is not a refusal. The examiner is telling you what has to change, or what information is missing, before they can issue. On residential files we see the same handful of items come back again and again: guard heights and openings on decks, stair headroom drawn without a dimension, beam and lintel sizes without supporting calculations or engineered product sheets, missing spatial separation calculations for windows close to a side lot line, and fire separation details between a basement suite and the main unit.

An Examiner's Notice is the City handing the clock back to you. Every week it sits unanswered is a week you're losing, not them.

Responding well is a skill. Answer every item, in order, and point to the exact drawing sheet where you made the change. A cover letter that says revised as requested, with no sheet references, tends to earn a second round. If you disagree with an item, say why and cite the Code article, because examiners do accept reasoned responses. Applications that go unanswered long enough can be closed out by the City, and the response window is set by the City, so confirm the deadline printed on your notice. When PermitsHub takes over a stalled file, the first thing we do is rebuild the drawings against the notice line by line so the resubmission clears in one pass.

Why Zoning and Building Review Show Up as Separate Lines

Inside one permit folder you'll often see multiple review lines, each with its own status. Zoning is one. Building (sometimes labelled plan review or structural) is another. Plumbing, HVAC and fire may appear too, depending on the project. They're separate because they test your drawings against completely different rules.

Zoning review checks the project against the city-wide Zoning By-law 569-2013 (or a former municipal bylaw still in force on some properties): height, setbacks, lot coverage, floor space index where it applies, parking, and the specific rules for things like garden and laneway suites. Building review checks the Ontario Building Code: structure, fire separations, egress, energy efficiency, stairs and guards. You can sail through one and fail the other. A rear addition can be perfectly engineered and still be half a metre too deep for the zoning, and a fully compliant zoning envelope can still have an undersized beam.

This is where projects stall hardest. If zoning review finds a variance is needed, the building permit can't be issued until you either redesign to comply or get approval from the Committee of Adjustment, which involves public notice to neighbours and a hearing. That turns a weeks-long permit into a months-long process. The zoning line showing not approved while building shows approved is the signal. Some owners avoid the surprise entirely by getting a zoning review or a Zoning Certificate before they submit, so they know early whether variances are in play.

Issued Isn't Finished: Open Inspections and Selling Your House

Once issued, the folder lists the required inspection stages for that project. For a typical addition that might include footings, foundation, structural framing, insulation and vapour barrier, plumbing and HVAC rough-ins, fire separations, and final. Each line shows whether it has passed, failed, been partially completed, or hasn't been booked yet. A permit can sit in this state for years if the owner simply never called for the final.

That's how open permits end up surprising sellers. A buyer's lawyer will typically search the property for outstanding permits and work orders. An open permit with missing inspections on, say, a basement finished eight years ago, or a deck nobody called the final on, can trigger a requisition. The buyer may ask for the permit to be closed before closing, a holdback, or a price adjustment. Closing an old permit isn't always quick. If walls are closed in, the inspector may ask you to open them up at the framing or insulation stages, or to provide an engineer's letter or other evidence that the work complies.

There's also the inactive permit problem. Under the Building Code Act, the City can revoke a permit if work hasn't started within six months of issuance, or if work has been substantially suspended for more than a year. If you're sitting on an issued permit and life got in the way, check the status before assuming it's still valid.

  • Before listing a house, search your own address and look for any folder not marked closed.
  • Read the inspection lines, not just the folder status, because a folder can look fine while one stage is still outstanding.
  • Book the remaining inspections early, since a final that fails on a small item like a missing handrail return means a second booking.
  • Keep inspection reports and engineer letters together, as they're what a buyer's lawyer and the inspector will ask for.

When the Status Hasn't Moved

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

A file that hasn't changed in weeks usually falls into one of three situations. First, the application was never deemed complete, so the review clock never started. Second, an Examiner's Notice went to the applicant of record (often the designer or contractor, not the homeowner) and nobody acted on it. Third, the file is waiting on another agency, such as TRCA on a ravine or floodplain lot, Urban Forestry where a protected tree is involved, or Transportation Services for a curb cut. These are applicable law approvals, and the building permit won't issue until they're in.

The fix starts with knowing which one you're dealing with. Ask whoever submitted the application for a copy of any notice they received. If you can't tell, the examiner's name on the file is your starting point, and Toronto Building's customer service can tell you what's outstanding. Across hundreds of Toronto files, from Leslieville semis to Etobicoke bungalows, the pattern we see most often isn't a slow City. It's a notice sitting unanswered in someone's inbox. PermitsHub regularly picks up files in exactly that state, handles the revisions and resubmission, and then coordinates inspections through to a closed permit.

The online status page won't tell you everything, but read properly it tells you who owns the next move. Check it weekly while your application is active, check every inspection line before you sell, and treat any notice as a to-do list rather than a rejection.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Permits 101

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT