Adding a Second Storey as a Separate Unit Under Toronto's Multiplex Rules
Toronto's multiplex rules let you put a new storey on a bungalow and rent it as its own unit without a rezoning. The zoning side is easier than most owners expect. The Building Code side is not. Fire separations, a second exit path and service upgrades turn a familiar addition into a small multi-unit building, and the permit drawings have to show all of it.
Key Takeaways
- Since Toronto amended Zoning By-law 569-2013 in 2023, a duplex, triplex or fourplex is permitted as-of-right in residential zones, so a new upper storey can be its own unit without a rezoning, but height, setbacks and other envelope rules still apply and can still trigger the Committee of Adjustment.
- Once the upper floor is a separate dwelling unit, the floor-ceiling assembly between units becomes a rated fire separation with sound control, which usually means opening up the existing bungalow ceiling and reworking ducts, pot lights and plumbing penetrations.
- Every unit needs its own protected path to the outside, and the stair is the design decision that drives everything else, so settle the stair location before finalizing the floor plan.
- Electrical, water and heating usually need upgrades or separation that a single-family addition never triggers, and the utility side of those upgrades often runs on its own timeline next to the permit.
Bungalow Plus One Unit
Yes. Under Toronto's multiplex amendments to Zoning By-law 569-2013, you can add a second storey to a bungalow and make it a separate rental unit, turning the house into a duplex or triplex without a rezoning. What changes is the Building Code side. A separate unit brings rated fire separations between floors, a protected exit for each unit, sound control and service upgrades that a regular family addition never needs. Your permit drawings have to show all of it.
That last part catches people off guard. Most owners treat the zoning approval as the hard part and the unit as a detail. In practice it works the other way around. The zoning envelope for a multiplex is usually the same one you'd have for a single-family addition. The building you put inside that envelope is a different kind of building, and plan examiners review it that way.
What the Multiplex Rules Changed, and What They Left Alone
In 2023, Toronto City Council amended the citywide zoning by-law so that duplexes, triplexes and fourplexes are permitted in residential zones, including the RD (residential detached) zones that cover most postwar bungalow streets. Council has since expanded permissions further in some wards, so confirm the current rules for your address. Before these amendments, turning a detached house into three or four units on many of these lots meant a zoning amendment or a long variance process. Now the use itself is allowed.
What the amendments did not do is hand you a bigger box. Height limits, side yard setbacks, building depth, and in some zones main wall height rules still govern the shape of the addition. A bungalow lot in Scarborough or Etobicoke with a height limit and tight side yards gets the same building envelope whether the upper floor is a primary bedroom suite or a two-bedroom rental. Floor space and density limits work differently by zone and building type, and this is one of the first things we check on any multiplex file, because it can decide whether the upper unit is a comfortable two-bedroom or a cramped one-bedroom.
Parking is one area that genuinely got easier. Toronto removed most minimum parking requirements in 2021, so adding a unit generally doesn't force you to find a second parking space on the lot. Provincial changes under Bill 23 also exempted additional units in existing houses from development charges in many cases. The details depend on unit count and configuration, so confirm with the City before you count on it.
The multiplex rules let you add a unit. They don't make the lot any bigger, and they don't make the Building Code any easier.
Three Ways to Configure a Bungalow With a New Storey
Most of the bungalows we see for this type of project are 1950s and 1960s brick or block homes with a full basement, built across North York, Scarborough and Etobicoke. That basement matters, because it means you're often deciding between two and three units, not one and two.
Duplex: owner on the main floor, rental upstairs
The simplest version. The main floor and basement stay as one unit, the new storey becomes the second. One fire separation, one new exit path, and the basement keeps its existing use.
Triplex: basement, main floor and upper floor as three units
This is where the economics usually point, and where the Code work multiplies. You now have two floor assemblies separating units, two sets of sound control, and three units that each need a protected way out. If the basement is already a legal second unit, it may have been approved under older or retrofit provisions, and an examiner will look at whether the whole building now meets the requirements for three units.
Upper unit combined with a rear addition
Some owners pair the new storey with a rear extension so the stair can be housed in new construction instead of being carved out of the existing floor plan. This often produces the cleanest layout, but it means designing to two sets of envelope rules (building depth at the rear, height at the top) at the same time.
The Floor Between Units Becomes a Fire Separation
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
In a family addition, the floor between the main level and the new storey is just a floor. In a multiplex, it's a rated fire separation between dwelling units, and it needs sound control too. The Code sets a minimum sound transmission rating between dwelling units (STC 50 is the long-standing benchmark, with apparent ratings now also part of the current Code). The fire-resistance rating depends on how many units the building has and how the house is configured. Two- and three-unit houses have specific provisions, and the right assembly for your building is something your designer should confirm against the current Ontario Building Code.
The practical consequence is that the existing bungalow ceiling usually has to come down or be built over. Plaster or single-layer drywall on old joists rarely qualifies as a listed rated assembly. Expect fire-rated drywall in a specific layer configuration, insulation in the joist cavity, resilient channels for sound, and careful detailing at every penetration.
Penetrations are where examiners and inspectors focus. Pot lights in a rated ceiling need rated housings or enclosures. Plumbing stacks and drains passing from the upper unit down through the floor need firestopping. Ductwork crossing between units is the big one. Shared forced-air systems between separate units are restricted, and the drawings have to show either separate heating systems or the protections the Code requires where ducts cross the separation.
Walls matter too. Wherever a stair or corridor serving the upper unit runs past the main-floor unit, the walls enclosing it are part of the separation, and so are the doors. Unit entrance doors in a fire separation need to be solid-core or rated as required and self-closing. That's a detail that shows up on inspection, not just in drawings.
Getting People Out: Exits and the Stair Question
Every dwelling unit needs a way out that doesn't pass through another unit. For an upper-storey unit, that means a stair to grade that either sits inside a fire-separated enclosure or runs down the outside of the building. Settle this decision before you finalize the floor plan, because it drives everything else.
- Interior stair in a separated enclosure: weatherproof and tidy from the street, but it takes floor area from the main level, and on a narrow bungalow that can wreck the main-floor layout.
- Exterior stair: frees up interior space, but it has to fit within setbacks, it may need a variance on a tight side yard, and it gets icy in February unless it's covered.
- Stair in a new rear or front addition: often the cleanest answer, but it adds footprint and its own zoning review.
Bedroom windows in the new unit also have to meet egress requirements unless the unit has other qualifying means of escape. Many designers try to squeeze a large upper unit into the envelope by tucking bedrooms under sloped ceilings with small dormer windows. That's the kind of design that gets a revision notice. Size the windows early, and remember that spatial separation rules limit how much glass you can put on a side wall close to the property line.
Services: Power, Water and Heat for Two or Three Households
A typical postwar bungalow was built with a modest electrical service that has already been stretched by air conditioning, a modern kitchen and maybe an EV charger. Adding a full unit with its own kitchen, laundry and heating usually means a service upgrade, and many owners want separate meters so tenants pay their own hydro. The upgrade runs through Toronto Hydro on one track and an ESA permit on another, separate from the building permit, and the utility timeline can run longer than the building permit itself.
Water is less obvious but worth checking. An older, smaller water service line feeding three bathrooms and three kitchens can produce weak pressure on the top floor. Each unit should also have its own accessible shut-off. Heating needs its own decision too. Separate systems per unit are the simplest way to satisfy the separation rules and give tenants their own thermostat, but they cost more up front and need room for equipment and venting.
How the Permit File Differs From a Regular Addition
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
A single-family second-storey application to Toronto Building is mostly about structure, envelope and zoning. A multiplex application adds a layer of life-safety review on top. The drawing set has to carry more information, and examiners will ask for it if it's missing.
- Unit layouts clearly labelled, with the use of every room in every unit, including the existing floors you aren't renovating.
- Fire separation locations shown on plans and sections, with the specific assembly referenced for each floor, wall and door.
- Exit paths drawn from each unit to the outside.
- Spatial separation calculations for walls with windows near property lines.
- Sound control assemblies between units.
- Mechanical drawings or notes showing how heating and ventilation stay separate between units.
- Structural drawings confirming the existing foundation and walls can carry the new storey, often with an engineer's review of the existing footings.
Designer qualifications also matter. Once a building has three or more units, the BCIN category a designer needs can change, and larger buildings can cross into territory that requires an architect. Check this before hiring anyone. The cheapest way to waste three months is to have drawings prepared by someone who isn't qualified to sign them for a triplex.
On the files PermitsHub prepares for bungalow conversions in North York and Scarborough, the most common first-round comments aren't about zoning at all. They're about missing fire separation details at the stair, ductwork crossing between units with no protection shown, and existing basement units that were never formally legalized. Fixing those before submission saves a full revision cycle.
Where These Projects Actually Stall
The first stall point is the basement. If you're going to three units and the basement suite was built informally years ago, the City will treat it as part of the application. That can mean ceiling height checks, egress windows, and fire separation upgrades in a space you thought was finished.
The second is the envelope. Owners plan the upper unit around the floor area they want, then find that height or main wall limits force a lower roofline or a stepped-back wall. Anything that goes beyond the as-of-right envelope still goes to the Committee of Adjustment. The multiplex use being permitted doesn't make neighbours any less likely to object to height, overlook or massing at a hearing.
The third is the existing structure. A new storey on a 70-year-old bungalow puts loads on footings and walls that were never designed for them. An engineer may call for underpinning or new posts and beams in the basement, which then collides with whatever is happening in the basement unit.
The fourth happens at inspection. Inspectors check what the drawings promised: firestopping at every penetration, self-closers on unit doors, interconnected smoke alarms across the units where required, and rated drywall installed the way the assembly specifies. Trades who mostly build single-family homes sometimes skip these. Getting your general contractor to walk the fire separation details with the drywaller before boarding begins prevents most failed inspections. When PermitsHub coordinates inspections on these jobs, that pre-board walkthrough is the step we push hardest for.
Nobody fails a multiplex inspection on the big stuff. They fail on a missing door closer and an unsealed pipe through the ceiling.