PermitsHubPermitsHub

New Construction

When Does a GTA Addition or New Build Need a Geotechnical Soil Report?

The Ontario Building Code lets designers size footings from tables, but only when the soil is what the code assumes it is. Across the GTA, buried ravine fill, soft clay, old Lake Iroquois sands and high groundwater regularly break that assumption. Here's how engineers decide when boreholes are needed, how additions differ from full rebuilds, and what it takes to get a drill rig onto a narrow infill lot.

By PermitsHub Team9 min read

Key Takeaways

  • Part 9 footing tables are only valid on firm, undisturbed native soil, compacted granular fill or rock, so any sign of old fill, soft clay, loose sand, high groundwater or a nearby slope pushes the design toward a geotechnical report.
  • Most modest single-storey rear additions on ordinary GTA till or clay go ahead without boreholes, while most full Toronto rebuilds with deeper basements now include a geotechnical report.
  • Second-storey additions usually hinge on the existing foundation, so the engineer often asks for a test pit beside the old footing rather than a full borehole investigation.
  • On narrow infill lots, rig access, utility locates and neighbour permission drive the schedule, so the investigation should be booked before the foundation design is finalized.

Soil Reports Before Footings

An addition or new home in the GTA needs a geotechnical soil report when the ground under the footings isn't the firm, undisturbed native soil the Ontario Building Code assumes. Part 9 lets a designer size footings straight from code tables on known, stable soil. Old fill, soft or sensitive clay, loose sands, a high water table, or a slope or conservation-regulated area all take you outside those assumptions, and an engineer will want boreholes before signing off. In practice, most full rebuilds in Toronto now get a report, and most modest rear additions on ordinary clay or till lots don't.

What Part 9 Lets You Assume About the Soil Under Your House

Part 9 of the Ontario Building Code covers most houses and additions. Section 9.4.4 deals with foundation conditions and lists allowable bearing pressures for broad soil categories such as dense sand or gravel, stiff clay, and rock. The footing size tables in Section 9.15 are built on top of that. They work as long as the footing sits on undisturbed soil, rock or properly compacted granular fill, below frost depth (typically 1.2 metres in the GTA). If the designer can reasonably identify the soil as one of those categories, no testing is required.

The catch is in the conditions. Where soil is unknown, contains organics or uncontrolled fill, is prone to movement from moisture or frost, or sits in groundwater, the code expects the foundation to be engineered instead of pulled from a table. An engineer can't design for soil nobody has looked at. Toronto Building and the suburban building departments don't demand a geotechnical report on every Part 9 file, but a plan examiner will ask for one when the site plan, grading, or a conservation authority comment points to trouble. Just as often, the structural engineer stamping the drawings refuses to rely on assumed values and asks for one before finishing the foundation design.

The code tables don't test your soil, they assume it. A geotechnical report is how you find out whether that assumption is true on your particular lot.

Five GTA Ground Conditions That Send an Engineer Looking for Boreholes

Old ravine fill and buried creeks

Toronto filled in a lot of its ravines more than a century ago. Garrison Creek once ran through what is now Christie Pits and Trinity Bellwoods. Taddle Creek wound through the Annex and the university grounds. Castle Frank Brook and sections of other small creeks were buried the same way. Houses went up on that fill, and on some streets the fill is several metres of cinders, brick, ash and organic material. The warning signs are familiar: neighbours with cracked foundation walls, floors that slope toward the back, a backyard noticeably lower than the street, or original houses sitting on deeper footings than their neighbours. Postwar suburbs have their own version, where builders in parts of Scarborough, North York and Etobicoke regraded lots with whatever fill was handy.

Soft clay and moisture-sensitive clay

Much of North York, Vaughan, Markham, Mississauga and Oakville sits on glacial till, which is generally excellent to build on. Mixed into it are pockets of soft clay, especially in low spots and along old watercourses, that compress under new load. Clay near large mature trees can also shrink as roots pull moisture out of it, and those trees are often protected, so removing them isn't an easy fix. The specific risk with an addition is differential settlement: the old house has finished settling decades ago, while the new footing starts settling the day it's loaded. That's where the crack at the joint between old and new comes from.

Lake Iroquois sands and the old shoreline

The Davenport Road hill is the old shoreline of glacial Lake Iroquois, and that shoreline continues east across the city into Scarborough. Below it you find beach deposits of sand, silt and gravel. Out by the Bluffs, Birch Cliff and Cliffside, sand dominates. Dense sand carries load very well. Loose sand, layered silts, and water perched on top of clay layers are a different story: excavation walls ravel, and pumped water moves through sand fast. North of the city, the Oak Ridges Moraine through Richmond Hill and King brings similar sandy, water-bearing ground.

A high water table

South Etobicoke (Long Branch, New Toronto, Mimico), the Beaches, and low areas near the Humber and Highland Creek routinely hit groundwater at basement depth. Water lowers the effective bearing capacity of soil and changes how the basement has to be drained and waterproofed. Excavating below it means dewatering, and discharging that water to a City sewer requires approval from Toronto Water, with provincial registration or permitting once volumes pass certain thresholds. The engineer needs an actual measured groundwater level to decide whether your basement can go as deep as the architect drew it.

Slopes and conservation-regulated areas

If your lot backs onto the Don, Humber, Rouge, Credit, Sixteen Mile Creek or any regulated valley, the Toronto and Region Conservation Authority, Credit Valley Conservation or Conservation Halton will likely want a slope stability assessment establishing the stable top of bank and any setback. That is geotechnical work, done by drilling near the slope crest. In Toronto, the Ravine and Natural Feature Protection bylaw adds its own layer on top of that.

Rear Addition, Second Storey or Full Rebuild: Where the Line Usually Falls

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

A single-storey rear addition on a lot with ordinary native soil, no fill history and no water problems usually goes ahead on table-sized footings. The real soil check happens at the footing inspection, when the inspector looks at the bottom of the excavation. If the ground looks like undisturbed native soil, you pour.

A second-storey addition is mostly a question about the existing foundation, not new soil. Many older Toronto houses sit on narrow brick or rubble footings that were never sized for an extra floor. The engineer will often ask for one or two test pits dug beside the existing footing to measure its width and depth and see what it bears on. That is far simpler than a borehole investigation, and it's usually enough.

A full rebuild is different. New homes typically come with deeper basements, foundations within a metre or so of the neighbours' walls, possible shoring or underpinning of adjacent footings, and dewatering. For that combination, a geotechnical report has become standard practice across Toronto and most of the 905, even where nobody formally demands it, because the engineer has too many decisions that depend on real soil data.

  • The lot sits on or near a known buried creek or a filled ravine.
  • The backyard is noticeably lower or higher than the street or the neighbours.
  • Neighbouring houses show foundation cracking or have been underpinned.
  • Sump pumps on the street run constantly, or nearby basements flood.
  • The design deepens the basement, adds a walkout, or digs below the existing footings.
  • The property is within a conservation authority regulated area or near a top of bank.

Getting a Drill Rig Into a Narrow Infill Backyard

This is the part nobody budgets time for. A standard truck-mounted rig won't fit down a 0.9 metre side yard between two semis. The options are a limited-access track-mounted rig, which still needs a fence panel or gate removed and sometimes a neighbour's side yard; portable or hand-operated auger equipment, which can't go as deep; test pits dug with a mini excavator; or drilling from the front yard or a rear lane. Laneway lots in Toronto have a real advantage here.

If the old house is still standing, nobody can drill under it. The driller works around the perimeter, and the engineer often notes that founding conditions must be confirmed once the house is demolished. Before any drilling, utility locates through Ontario One Call are mandatory, and on a tight lot, a gas service or buried hydro line can force borehole locations to move. Where groundwater matters, monitoring wells are left in the holes and read again after the water level stabilizes, which adds time.

The cost drivers follow from all of this: how hard the access is, how many holes and how deep, whether wells are installed, and how much lab testing the engineer wants. A small rig is slower per metre than a full-size one. The scheduling lesson is simple. Book the investigation while the design is still flexible, because the report may change footing depth, basement depth, or the whole foundation system.

What the Report Contains and How It Shows Up on Your Permit Drawings

  • A borehole location plan tied to the site survey.
  • Borehole logs showing each soil layer, its depth, and standard penetration test blow counts.
  • Groundwater observations during drilling and from any monitoring wells.
  • Recommended bearing resistance values and the depth at which they apply.
  • Recommendations on excavation, shoring, dewatering, backfill, perimeter drainage, slab support and frost protection.

The structural drawings reference the report by its number and date. The footing schedule is sized to the recommended bearing values, and the general notes typically require the geotechnical engineer to inspect the founding soil before concrete is placed. Plan examiners do read for consistency. If the report calls for footings at a certain depth and the sections show something shallower, or the report recommends underfloor drainage that the drawings omit, expect a comment and a resubmission. At PermitsHub we cross-check footing sizes, depths and drainage details against the geotechnical recommendations before submission so those mismatches don't cost you a review cycle.

What Happens When You Skip It and the Footing Inspection Goes Wrong

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

The Building Code requires an inspection before footings are poured. Picture the inspector arriving at the excavation and finding a black organic layer, broken brick and cinders, soft wet clay, or water filling the trench. The pour stops. An engineer has to attend and decide what to do: dig deeper to competent soil, over-excavate and replace with engineered fill, or switch to helical piles or another deep foundation. The concrete truck gets cancelled, the crew sits, and revised drawings may need to go back to the building department.

None of that is rare. We see it most often on lots along the old buried creek routes in the west end, where PermitsHub has handled enough files that we now flag fill risk during the initial zoning and site review instead of waiting for an inspector to find it. A report done up front doesn't make bad soil go away. It turns it into something you design and price for before construction, instead of something you discover with an excavator idling in the yard.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

New Construction

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT