Submitting a GTA Building Permit in December and the Holiday Backlog
The Ontario Building Code gives your municipality a set number of business days to review a permit, and the holidays aren't business days. A December submission can still get you to a spring start, but only if the first review comes back clean. If it doesn't, your revisions join the January wave of spring-project applications.
Key Takeaways
- The Ontario Building Code review timeframes count business days, so statutory holidays and any days the building department is closed to the public over Christmas and New Year do not count toward the review period.
- The review clock only starts once the municipality accepts the application as complete, so a December file that still needs a minor variance, TRCA permit or heritage clearance is not on the clock at all.
- Most of the real delay comes after the holidays, when revisions, permit issuance and inspection bookings compete with the January surge of spring-project submissions.
- A December submission saves meaningful time only when the drawing package is complete and someone is available to answer examiner comments through the holiday weeks.
The December Permit Gamble
A building permit submitted in December in Toronto or the GTA usually takes longer on the calendar than the same file submitted in October, even though the legislated review time is identical. The Ontario Building Code counts review timeframes in business days, so Christmas, Boxing Day, New Year's Day and any days the building department is closed to the public don't count. A ten-day review on a house that starts in mid-December often doesn't produce a decision until the first or second week of January. Then the January rush of spring-project applications slows everything that comes after the first review: your resubmission, permit issuance and inspection bookings.
That doesn't mean December is a bad month to apply. It means December rewards a complete, well-coordinated package and punishes a rushed one harder than any other month of the year.
How the OBC Review Clock Treats Christmas and New Year
Division C of the Ontario Building Code sets mandatory timeframes for a municipality to either issue a permit or refuse it with reasons once a complete application has been filed. For a house, the timeframe is 10 days. Small buildings get 15, large buildings 20 and complex buildings 30. Those are not calendar days. The code excludes weekends, statutory holidays and other days when the chief building official's office isn't open to the public.
So over the holidays, Christmas Day, Boxing Day and New Year's Day drop out automatically. If your municipality closes its building department between Christmas and New Year, those days drop out too. Toronto, Vaughan, Markham, Richmond Hill, Mississauga and Oakville each set their own holiday schedules, and staffing on Christmas Eve and New Year's Eve is often thin even when the office is technically open. Check your municipality's posted holiday hours before you count days.
The clock you see versus the clock the city counts
Homeowners usually count from the day they hit submit. The municipality counts from the day the application is deemed complete. Between those two dates there's an intake and completeness check, and in Toronto that includes confirming you've supplied what zoning review needs. If anything is missing (a current survey, an energy efficiency compliance form, HVAC design documents, a signed designer schedule), the clock never starts. It just sits.
Applications that depend on other approvals have it worse. The code won't treat a permit application as complete until applicable law is satisfied. A rear addition that needs a minor variance from the Committee of Adjustment, a house in a TRCA regulated area or a property inside a heritage conservation district can't get a decision until those approvals are in hand. Those bodies slow down over the holidays as well, and Committee of Adjustment hearing calendars typically pause through the end of December.
A December submission isn't a head start if the examiner's comments land on December 23rd and nobody answers them until January 11th. It's a head start only when the first review comes back clean.
A December Submission, Week by Week
Here's how a typical house file plays out when it goes in during December. The exact dates shift every year depending on which weekday Christmas falls on, but the pattern holds.
- First week of December: the application goes through intake. If it's complete, the 10-day clock starts, and a decision can realistically arrive before the holiday slowdown.
- Mid-December: a file accepted now will burn a handful of business days before Christmas, then stall. Examiners are also clearing their own desks before time off, so the first review may be thorough but late in the window.
- Christmas to New Year: statutory holidays don't count, and reduced staffing means little moves even on the days that do. Designers and engineers are often away, which matters if comments arrive.
- First two weeks of January: decisions on December files come out alongside a fresh stack of new spring-project applications. If you get a notice listing deficiencies, your revisions join that queue.
- Late January into February: resubmission reviews, permit issuance and fee payment happen here for most December files that needed revisions. Inspection booking demand starts climbing as contractors line up spring starts.
The thing most people miss is that the legislated timeframe covers the first decision, not the whole permit. On residential files in the GTA, that first decision is very often a list of examiner comments rather than an issued permit. Every round of revisions gets its own review, and in January those reviews compete with everyone else's.
Why the January Wave Lengthens Every Queue
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
Homeowners decide on spring projects over the holidays. Designers spend December finishing drawings for those clients. Contractors want permits in hand before they commit crews for April. The result is a spike in residential submissions through January and February, landing on examiners who are also working through everything held over from December.
Revisions feel this most. A response to examiner comments filed on January 6th doesn't jump the line because the original application went in on December 10th. In practice, a December applicant who needs two rounds of revisions can end up with an issued permit around the same time as a well-prepared applicant who submitted cleanly in mid-January.
There's also a money angle to the new year, even though it doesn't change the timeline. Many municipalities update permit fees through their annual fee bylaws, and development charges on new homes and some additions are indexed periodically. The rate that applies generally depends on when the permit is issued, not when you applied, so a December application that gets issued in February may be charged under the new schedule. Confirm with your municipality which rules apply to your file and when.
Inspections Are Where Winter Actually Costs You
Even a permit issued quickly in December doesn't guarantee an early start. Exterior work runs into winter conditions that inspectors won't overlook. Footings can't bear on frozen soil, and the code requires concrete to be protected from freezing while it cures. If a footing inspector arrives and finds frost in the excavation or uncovered concrete, expect a failed inspection and a rebooking.
Booking demand matters too. Inspection requests in most GTA municipalities run through an online system or a phone line, and turnaround is usually reasonable in the quiet months. As spring approaches, every contractor who got a winter permit wants footing and framing inspections at once. If your project depends on a tight sequence (excavate, footing inspection, pour, foundation inspection, backfill), a day or two of extra wait at each stage adds up.
Interior projects are different. A basement second suite, a kitchen wall removal with a new beam or an interior reno can start in January and keep moving through the winter, because cold weather barely touches them. For those projects, a December submission really can buy you a winter build.
When a December Submission Actually Saves Time
Use this as a quick test before deciding whether to rush a file in before the holidays or hold it for a cleaner January submission.
- Submit in December if the drawings are complete, zoning has been checked and the project complies as of right, with no variance or conservation authority approval needed.
- Submit in December if the work is interior and your contractor can start in January or February.
- Submit in December if your designer or permit consultant will be available over the holidays to answer comments within a day or two.
- Hold until January if the drawings still have open questions, such as an undesigned beam, missing truss layouts or no heat loss calculations yet.
- Hold, or file the Committee of Adjustment application first, if the project needs a minor variance, since the building permit can't be decided until that's resolved.
- Don't count on a December application to speed up an exterior foundation project; frost and spring inspection demand will set the pace more than the permit date.
The worst outcome is an incomplete December submission. It doesn't start the clock, it rarely gets flagged quickly over the holidays, and by the time you learn what's missing you're filing into the January peak anyway.
Setting Up a December File So It Doesn't Sit
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
Most December delays trace back to a short list of predictable problems. Fix these before submission and the holidays become a pause rather than a setback.
- Aim to submit in the first week of December so that the full review window can run before the slowdown.
- Include a current survey, a site plan with setbacks dimensioned against the zoning bylaw, and full floor plans, sections and elevations.
- Attach the energy efficiency compliance documents and HVAC design (heat loss and duct design) for any new home or addition, because missing mechanical paperwork is a common reason files get held at intake.
- Get engineering for beams, point loads and any removed bearing walls signed and stamped before submission, not promised later.
- Line up who will answer examiner comments between December 22nd and January 5th, and make sure they have the source drawing files, not just PDFs.
- Book your contractor for a realistic start date that allows for at least one round of revisions in January.
This is the part of the season we plan around at PermitsHub. When we prepare and submit drawings in late fall, we keep revision coverage through the holiday weeks, so comments that arrive just before Christmas get answered and resubmitted on the first business day the department reopens rather than in the second week of January.
The pattern has been consistent across the files we've run in Toronto, Vaughan, Markham and Mississauga. Clean December submissions on houses and interior work often come back issued or close to it by mid-January. December files that went in incomplete or needed a variance tend to be indistinguishable from ones filed in February. If you're not sure which group your project falls into, a PermitsHub zoning and drawing review before submission will tell you whether December gains you anything or whether a clean January filing is the smarter move.