PermitsHubPermitsHub

Permits 101

Stair Rise, Run and Headroom Rules That Fail Ontario Building Inspections

Under the Ontario Building Code, a stair inside a house needs risers between 125 mm and 200 mm, a run of at least 210 mm and 1950 mm of headroom. Getting those numbers right on paper is easy. Basement stairs fail anyway, because new flooring changes the top and bottom risers, ducts eat the headroom and handrails go in at the wrong height after the inspector has left.

By PermitsHub Team10 min read

Key Takeaways

  • Stairs inside a house in Ontario need risers of 125 mm to 200 mm, a run of at least 210 mm, tread depth of at least 235 mm, 1950 mm of headroom and a handrail 865 mm to 965 mm high measured from the nosing line.
  • The most common basement stair failure is an uneven top or bottom riser caused by finished flooring that wasn't accounted for when the stringers were cut, and the tolerance between adjacent risers is only about 5 mm.
  • Headroom is measured vertically from a sloped line through the tread nosings, so a duct, beam or bulkhead crossing the stair opening can fail the stair even when the rest of the basement ceiling is fine.
  • Stair problems are cheap to fix at the framing inspection and expensive after drywall, so the finished floor heights and the obstruction above the stair should be resolved on the permit drawings first.

Rise, Run and Headroom

For a stair inside a single house, the Ontario Building Code requires each riser to be between 125 mm and 200 mm high, each run to be between 210 mm and 355 mm, each tread to be at least 235 mm deep, at least 1950 mm of clear headroom above the stair and a handrail between 865 mm and 965 mm high. The stair also has to be uniform: adjacent risers and treads can only differ by a few millimetres. The failures we see most on GTA renovations are not the headline numbers. They're uneven top and bottom risers after new flooring goes down, headroom lost under a duct or beam, and handrails that are too low, too high or broken partway down the flight.

The stair numbers an inspector actually measures in a house

Part 9 of the Building Code splits stairs into two groups. Stairs serving a single dwelling unit (the code's term is private stairs) get the more generous limits below. Stairs serving more than one unit, like a shared stair to a basement apartment in some layouts, get tighter rules. These are the figures that apply to a typical house stair. Confirm against the current code edition for your permit, because the inspector will work from the edition your permit was issued under.

  • Rise: 125 mm minimum, 200 mm maximum, measured vertically from nosing to nosing.
  • Run: 210 mm minimum, 355 mm maximum, measured horizontally from nosing to nosing.
  • Tread depth: 235 mm minimum, which is why a run of 210 mm only works with a nosing projection.
  • Width: 860 mm minimum clear width for a stair within a dwelling unit.
  • Headroom: 1950 mm minimum, measured vertically from a sloped line drawn through the front edges of the treads.
  • Handrail height: 865 mm to 965 mm, measured vertically from that same nosing line.
  • Uniformity: roughly 5 mm maximum difference between adjacent risers or treads, and about 10 mm between the tallest and shortest in a single flight.

Inspectors carry a tape and a level, and on stairs they use both. They'll check the bottom riser, the top riser and a couple in the middle. They'll stand on a tread and look up at whatever is crossing the opening. And at final, they'll put a hand on the rail and walk it. If you only remember one thing from that list, remember the uniformity rule. It's the one people don't know exists, and it fails more stairs than the 200 mm maximum ever does.

Uneven risers: the failure that new flooring creates

Here's how it happens. A carpenter rebuilds the basement stair during the framing stage. He measures from the concrete slab to the subfloor upstairs and divides that height evenly into risers. Every riser is perfect. Then the basement gets a subfloor system and vinyl plank, which can add 20 mm or more on top of the slab. Upstairs, the owners put in new hardwood over the old floor. The bottom riser is now shorter than the others, the top riser is taller, and both are well outside a 5 mm tolerance.

This is the single most common stair deficiency we see on basement permits. It's also completely predictable. The fix is to cut the stringers to finished floor heights, not structural heights. That means somebody has to decide, before the stringers are cut, exactly what flooring is going on the basement slab and what's going on the main floor landing, including any underlayment, membrane or self-levelling compound.

Stringers should be cut to the floor you'll walk on, not the floor that's there when the carpenter shows up. Most riser failures are really a missing decision about flooring.

Why it's expensive to fix later

Once treads are glued and screwed, the stair is skirted, and drywall runs along both sides, correcting one riser usually means rebuilding the whole flight. You can't just shim one step, because shimming changes that tread's height relative to the next one and moves the problem up the stair. Sometimes a thinner floor finish at the bottom saves the day. More often the stair comes out, the drywall on the stair walls gets patched, and the finish carpenter comes back. Compared with getting it right at framing, it's meaningfully more work, and it often holds up the final inspection on everything else in the basement.

Headroom lost to ducts, beams and bulkheads

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Headroom catches people because of how it's measured. It isn't the ceiling height in the basement. It's the vertical distance from a sloped line through the tread nosings up to the lowest thing overhead, and that 1950 mm has to be maintained along the full length of the stair. The tightest spot is usually a few steps down from the top, right where the stair passes under the edge of the floor opening, a main beam or a trunk duct.

Postwar bungalows in Scarborough, Etobicoke and North York are the classic case. The basement stair runs under the main floor, the original warm air trunk crosses near the top of the opening, and the steel beam sits a step or two further down. The original stair might have had marginal headroom for 70 years. Once you rebuild it, or once a contractor adds a bulkhead to hide new plumbing, it has to meet the current number. Older semis and narrow houses in East York and the west end have a different version: the basement stair sits directly under the main stair, so the underside of the stair above is the obstruction.

Options when the headroom doesn't work

  • Reroute the duct. Splitting a trunk into two shallower runs, or moving it to the other side of the beam, often recovers what you need. An HVAC designer has to confirm the airflow still works.
  • Change the stair. Shifting where the stair starts, adding a landing or turning the run can move the tight spot out from under the obstruction, but every change ripples into the rise and run.
  • Enlarge the floor opening. Cutting the opening longer at the top means new headers and possibly a beam change, which needs structural design on the drawings.
  • Replace a dropped beam with a flush beam. This is the biggest structural move and needs an engineer, but it can solve headroom over the stair and in the rest of the basement at once.

The mistake we see is a bulkhead added after the framing inspection, usually to box in a new drain line or a sprinkler pipe, that drops right into the stair headroom. If anything new is going to run across the stair opening, it needs to be on the drawings and inspected where it sits.

Handrails: wrong height, broken runs and nothing to grip

Handrails usually go in near the end of the job, after the inspector has already signed off framing. That's why they fail at final. Three problems account for nearly all of them.

Height first. The 865 mm to 965 mm range is measured vertically from the nosing line, not from the back of the tread or from the floor at the bottom. Installers who measure from the tread surface at the wall, where it meets the riser, end up low. Brackets screwed into the drywall at a convenient stud height often end up somewhere in between, which means part of the rail passes and part doesn't.

Continuity second. The rail should run the full length of the flight, from the bottom riser to the top one, without a break you'd have to let go at. A rail that stops two steps short of the top because there's a door frame in the way, or one that's split into two pieces with a gap at a stud, is a common call. Where the stair has a landing, check with your examiner how your municipality wants it handled before the finish carpenter starts.

Grip and clearance third. A flat 1x4 screwed to the wall isn't a handrail. The code expects a graspable profile (a round rail is typically in the 30 mm to 43 mm diameter range) and enough clearance between the rail and the wall that your knuckles don't scrape, generally at least 50 mm. A rail mounted too tight to a textured or stone-clad wall fails on clearance even if the height is perfect. The rail also has to resist load, which means brackets into framing or proper blocking, not drywall anchors.

Guards, landings and the door at the top of the stair

When a basement stair is opened up on one side, it picks up guard requirements. Generally a guard is needed where the drop beside the stair or landing is more than 600 mm, and inside a dwelling unit the guard is typically at least 900 mm high. Openings in the guard can't let a 100 mm sphere pass through, and it shouldn't be built so a child can climb it. Horizontal cable or rail designs that look great in a magazine are the ones that get written up.

The other flag is the door at the top. If the door to the basement swings over the stairs, you need a landing so nobody opens it and steps into air. A door swinging away from the stair, into the hallway or kitchen, generally avoids that problem. Old houses often have a door that swings toward the stair onto the top tread. Keeping it during a renovation that rebuilds the stair is a common mistake, and the simple fix is usually to rehang it the other way.

Existing stairs versus rebuilt stairs

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

A common question: does finishing a basement force you to rebuild a steep old stair? Not automatically. Part 11 of the Building Code deals with renovations to existing buildings and allows existing conditions that aren't being altered to stay in many situations, with compliance alternatives for some elements. But once you tear out the stair, change its location, or alter it as part of the permit work, the new stair is generally expected to meet current requirements. Creating a secondary suite raises the bar further, because the stair may now serve more than one unit and may need fire separation around it.

The answer depends on the scope written on your permit and how your examiner reads it, so it's worth settling during plan review rather than at the framing inspection. When PermitsHub prepares basement drawings, we show the stair with finished floor heights at top and bottom, the calculated rise and run, and the headroom line drawn against the actual beam and duct locations. That way the examiner's questions come back on paper, where they're cheap to answer.

Catch it at framing, not at final

The framing inspection is the moment that matters for stairs. The stringers are exposed, the opening is visible, and the ducts and beams are where they'll end up. If the stair isn't built yet when you call for framing, ask whether the inspector will come back to check it before you close the walls. Many will, and it costs far less than an order to open things up later.

  • Before cutting stringers, confirm the exact finished floor build-up at the top and bottom of the stair.
  • Before booking framing, measure headroom from the nosing line under every duct, pipe and beam crossing the opening.
  • Before drywall, add solid blocking in the stair wall where the handrail brackets will land.
  • Before final, measure the rail height at the top, middle and bottom from the nosing line, and walk it end to end.

Across hundreds of basement permits in the GTA, from Etobicoke bungalows to Markham backsplits, the pattern holds: the stairs that pass were designed with the finished house in mind. If you're partway through a project and something on the stair looks off, PermitsHub can review the drawings and the site conditions against the code before your next inspection is booked.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Permits 101

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT