Can You Rebuild a Scarborough Detached Garage on Its Old Setbacks?

That old block garage tight to your side lot line is probably legal only because it already exists. Tear it all the way down and, in most cases, the protection goes with it. Here is how Toronto treats a Scarborough garage rebuild, when you need a variance to keep the old spot, and what changes on a Bluffs lot.

By PermitsHub Team10 min read

Key Takeaways

  • A Scarborough garage that sits closer to the lot line than By-law 569-2013 allows is usually protected only as a lawfully existing building, and full demolition generally ends that protection.
  • If you want the new garage on the old footprint and the old setbacks don't meet current zoning, plan on a minor variance from the Committee of Adjustment Scarborough panel before your building permit can be issued.
  • A wall close to the lot line brings Ontario Building Code issues of its own, such as fire-resistance requirements, limits on openings, and keeping roof drainage and eaves on your own property.
  • On lots near the Scarborough Bluffs, confirm TRCA regulation and any slope stability requirements first, because they can move or shrink the garage before zoning even comes into play.

Same Spot, New Garage

Usually not automatically. A detached garage in Scarborough that sits closer to the side or rear lot line than Toronto Zoning By-law 569-2013 now permits is generally allowed to stay because it lawfully existed before the current rules. That protection is tied to the building itself. Once you demolish the garage completely, the new one is treated as new construction and has to meet today's setbacks, unless you get a minor variance from the Committee of Adjustment to put it back where the old one stood. Lots near the Bluffs may also need TRCA approval before the City will issue anything.

Why the old garage is allowed to sit where it sits

Most of the garages we see in Wexford, Dorset Park, Clairlea, Birchcliff and Cliffside went up in the 1950s and 1960s alongside the bungalow or side-split in front of them. They were approved under the former Borough of Scarborough by-laws, which were a patchwork of area-specific rules, and many of those rules let a single-car garage sit very close to the lot line. Some were built with the eaves practically touching the neighbour's fence. A few were never permitted at all.

When the City adopted By-law 569-2013 after amalgamation, the setback rules for ancillary buildings changed. A garage that complied in 1958 may not comply now. The by-law deals with this by recognizing buildings that were lawfully built under the rules of their day. The garage is legal non-conforming: it doesn't meet the current numbers, but it's allowed to remain.

Two caveats come up constantly. First, "lawfully built" matters. If the garage was put up without a permit, or was enlarged later without one, it may not have protection at all. Second, some Scarborough properties are still partly governed by the former borough by-laws because of how 569-2013 was rolled out and appealed. Before you plan anything, confirm which by-law actually applies to your lot and what it says about ancillary buildings.

What happens to that protection when the garage comes down

Legal non-conforming status protects something that exists. It doesn't reserve a spot on your lot for a future building. Once the garage is demolished, there's nothing left that's non-conforming, just a slab or a patch of gravel, and any new garage has to meet the setbacks, height limits and coverage rules in force on the day you apply.

Homeowners are often caught off guard here because the logic feels backwards. They're replacing a rotting garage with a better one in the same place, so why should that be harder than leaving the eyesore alone? The zoning examiner isn't judging whether the new garage is an improvement. They're checking the drawings against the by-law, and a new structure close to the lot line fails that check on paper.

The protection belongs to the old walls, not to the patch of ground they stand on. Knock the walls down and you're starting from today's rulebook.

Another detail people miss: the plans examiner compares your proposal against what's legally on record, not against what the neighbours remember. If there's no permit history for the existing garage, be ready to show it has been there a long time. Old surveys, aerial photos and mortgage documents with a building location sketch all help.

Repair, partial rebuild or full demolition: where the line falls

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

There's a real difference between repairing a non-conforming garage and replacing it. Fixing the roof, re-cladding, replacing a sill plate or swapping the overhead door generally keeps the existing building, and its status, intact. Removing everything down to the slab and framing new walls is a new building, whatever you call it on the application.

The grey zone is where projects get into trouble. A homeowner applies to repair the garage, the contractor finds the block walls are cracked through and the slab has heaved, and the walls come down mid-job. Now the work on site no longer matches the permit. Inspectors notice, and the job can be stopped until the zoning question is resolved. If there's any real chance the structure won't survive the repair, sort that out before you apply, not halfway through.

  • Usually treated as repair: new roofing and sheathing, new siding, replacing individual damaged studs or rafters, a new garage door, electrical upgrades under an ESA permit.
  • Usually treated as new construction: removing all walls and the roof, pouring a new foundation or slab, enlarging the footprint, raising the height.
  • Case by case: replacing one wall entirely, replacing the roof structure with a new pitch, rebuilding on the existing slab with new walls.

Changing the shape also counts against you. A taller roof, a loft, a wider door bay or a few extra feet toward the house all mean the new garage isn't simply the old one rebuilt. Even if the setback stays the same, every other change gets measured against current rules.

Getting the old setbacks back through a minor variance

If you want the new garage in the old position and that position doesn't meet current zoning, the route is a minor variance application to the Committee of Adjustment. Scarborough properties go to the Scarborough panel. The application is decided against the four tests in the Planning Act: the variance has to be minor, desirable for the appropriate development of the land, and keep the general intent of both the Official Plan and the zoning by-law.

Garage setback variances are among the more approvable applications the Committee hears, especially when you're putting back what was already there. They aren't automatic, and the order of steps matters. You normally need drawings and a zoning review that list exactly which provisions you don't meet before you file, and the building permit generally can't be issued until the variance decision is final and the appeal period has passed. Budget months, not weeks, for this part. Confirm current filing requirements and fees with the City.

What the Scarborough panel and neighbours tend to focus on

  • Whether the new garage is the same size and height as the old one, or noticeably bigger. A like-for-like rebuild is a much easier conversation than one that adds a second storey or a loft.
  • Drainage onto the neighbouring lot. A roof that slopes toward the fence with no gutter is the most common neighbour objection we hear.
  • Maintenance access. If the wall is on or very close to the line, how will you repair it without going onto the neighbour's property?
  • Whether the garage will be used as living or workshop space later. A sink, windows facing the neighbour or a tall loft raise suspicion even when the application says storage.
  • Shared or mutual driveways, which are common in parts of Birchcliff and Cliffside and can complicate both access and the location.

Talk to the neighbour on that side before you file. A short letter of support, or simply making sure they aren't surprised by the notice sign on your lawn, does more for a garage variance than almost anything you can put in the drawings.

Building Code problems that follow a garage close to the lot line

Zoning is only half of it. Even with a variance, the new garage has to meet the Ontario Building Code, and a wall close to the property line brings its own requirements. Expect the plans examiner to look at spatial separation and fire protection for that wall, which can mean limited or no window and door openings on that side and fire-rated construction. Confirm with Toronto Building how the rules apply to your specific design, because the requirements depend on distance, wall area and use.

Eaves and gutters are the other recurring comment. The old garage's overhang may already cross the lot line. A new one can't. Rainwater from the roof has to stay on your property and drain away from your neighbour's lot. On tight Scarborough side yards that often means a shallower overhang, a different roof slope or a gutter that discharges toward your own yard.

Foundations are where old and new differ most. Plenty of post-war Scarborough garages sit on a thin slab with no proper frost protection, which is why the walls crack and the door won't close. A new garage needs a foundation designed to current standards, and on clay soils or near trees that may mean deeper footings or a thickened-edge slab with engineering. If a neighbour's large tree is close to the line, Toronto's private tree by-law can apply to excavation within its root zone. That can mean an arborist report and limits on digging that shift where the new foundation can go.

Bluffs lots: deal with TRCA before you finalize the design

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

If your property backs onto or sits near the Scarborough Bluffs or one of the ravines running into them, part or all of it may fall within an area regulated by the Toronto and Region Conservation Authority. TRCA regulates development near hazards like unstable slopes and erosion-prone shorelines, and replacing a garage counts as development in that sense. The City generally won't issue a building permit for regulated land until TRCA has signed off.

What TRCA cares about is the stable top of slope and a setback from it, not your zoning setbacks. On lots in Guildwood, Cliffside and along Kingston Road's lakeside streets, a garage that has stood near the back of the lot for sixty years may now sit inside the area where new construction is discouraged. TRCA may ask for a geotechnical slope stability study and may push the replacement garage toward the street, which can then create a new zoning conflict in the front or side yard. Sort out the TRCA position first and design the zoning around it, never the other way round.

Some Bluffs and ravine properties are also covered by the City's ravine and natural feature protection by-law, which has its own permit for grading and tree removal. Check both maps early.

A sequence that keeps your options open

The most expensive mistake we see is demolishing first and asking questions later. Once the old garage is gone, you can't get the existing-building argument back, and you'll be making your case to the Committee with nothing standing on site. A sensible order looks like this:

  • Get a current survey showing the existing garage, its setbacks, roof overhangs and any trees near the line.
  • Confirm which zoning by-law governs the lot and whether the garage has permit history or other evidence that it was lawfully built.
  • Check TRCA and ravine mapping, and if the lot is regulated, open that conversation before finalizing the design.
  • Decide honestly whether you're repairing or replacing, with a contractor or engineer looking at the walls and slab.
  • Prepare drawings and have them reviewed against current zoning so you know exactly which variances, if any, you need.
  • File the variance if required, then the building and demolition permits, and only take the old garage down once you have approval.

PermitsHub has run garage replacements on this exact type of Scarborough lot, from Wexford bungalows with block garages on the side line to Cliffside properties where the slope set the limits. Our usual first step is a zoning review against the survey, so you know before spending anything on demolition whether the old spot is realistic, needs a variance, or should move.

If the review shows the old position won't fly, moving the garage a little further from the line is often quicker than fighting for the old spot. A small shift can remove the need for a variance, relax the fire-separation requirements on that wall and solve the drainage problem at the same time. Weigh that against the yard space you'd lose. If your heart is set on the original footprint, PermitsHub can prepare the variance drawings and handle the Committee filing alongside the building permit, so the two applications move together instead of one waiting on the other.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Garage

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT