By Area
Rear Addition on a 1960s Islington or Markland Wood Home (M9B, M9C)
On a 1960s detached house in M9B or M9C, the limit on a rear addition is usually set by what's already on the lot: an old sunroom, an enclosed porch, a garage. Creek valley lots also need a TRCA permit before the City will release the building permit. Here's how to figure out how far back you can actually go, and which approvals you'll need before you start.
Key Takeaways
- On most 1960s Islington and Markland Wood lots, the first limit you hit is lot coverage already used by older sunrooms, enclosed porches, sheds and garages, not the rear yard setback.
- Lots near Etobicoke Creek or other valley lands in M9B and M9C can fall inside TRCA's regulated area, and the City treats a TRCA permit as applicable law, so the building permit can't be issued until TRCA signs off.
- Any shortfall on coverage, building depth or rear yard setback means a minor variance from the Committee of Adjustment's Etobicoke York panel, and on ravine lots TRCA comments on that application as well.
- Backsplits, walkouts and existing basement suites create design problems that examiners send back on, especially buried egress windows and new foundations sitting beside shallow 1960s footings.
Extending Toward the Creek
How far you can extend the back of a 1960s detached home in Islington or Markland Wood is usually decided by four things: the lot coverage you've already used, the minimum rear yard setback, the maximum building depth in Toronto's Zoning By-law 569-2013, and, on lots near Etobicoke Creek or other valley lands, the Toronto and Region Conservation Authority. If the addition breaks any zoning limit, you need a minor variance from the Committee of Adjustment. If the lot is inside TRCA's regulated area, you need a TRCA permit. The City will not issue the building permit until both of those approvals are in place.
That's the short version. The long version depends on what's already sitting on your lot, and in M9B and M9C that's often more than owners expect.
Take Stock of What the Last Sixty Years Added to Your Lot
Most Markland Wood and Islington houses went up between the late 1950s and the early 1970s. You see a lot of brick bungalows, raised bungalows, backsplits and sidesplits, many with attached garages and wide frontages. They look roomy, but they've had sixty years of owners. In that time a lot of them picked up a rear sunroom, an enclosed porch, a family room bumped out over a crawlspace, a large shed, or a garage that was rebuilt bigger than the original.
All of that counts. When a plan examiner checks lot coverage, they add up the footprint of every building and covered structure on the lot, not only the main house. We regularly see owners who planned a generous family room across the back and then find most of their coverage already used by a 1980s three-season room and a double garage.
Basement suites matter too, even though a suite sits inside the existing footprint. Many houses in these neighbourhoods have a second unit downstairs, legal or not. A rear addition can bury the basement bedroom window the suite relies on for egress. It can also block the side or rear entrance stairwell, or cut through the fire separation between units. Examiners check all three. If the suite was never permitted, a rear addition application tends to bring that to the surface, so it's better to deal with it at the design stage.
- Get a current survey, not the one from the 1960s purchase file. The old one won't show later additions, sheds or decks.
- List every structure on the lot with its footprint: house, garage, sunroom, enclosed porch, covered deck, shed.
- Note which of those have permits on record. Unpermitted structures still count toward coverage and can still draw an order.
- If there's a basement unit, mark its egress windows, entrance and the existing fire separation on the floor plan before anyone sketches the addition.
The Zoning Limits That Decide How Deep You Can Build
Most of these streets are zoned Residential Detached (RD) under City-wide Zoning By-law 569-2013. Some lots still have exceptions or transition provisions that send the examiner back to the former Etobicoke zoning code, so don't assume the general rule applies to yours. Check the zoning map and any site-specific exceptions first.
Lot coverage
In the RD zone, maximum lot coverage is set by an overlay map, so the percentage differs from one part of Etobicoke to another. Multiply your lot area by that percentage, subtract everything already built, and what's left is your room for the addition. On many Markland Wood lots that number turns out small. If you're already over the limit because the house or an old addition predates the current rules, you're in legal non-conforming territory. Building more usually means asking for a variance.
Rear yard setback and building depth
The rear yard setback is generally tied to lot depth with a minimum distance in metres. Building depth is measured back from the required front yard setback, and for detached houses in the RD zone it's commonly capped at 19 metres. Confirm both against the by-law and your lot's exceptions. Lots in Markland Wood and around Islington are often deep, so the rear yard setback is rarely the limit. Building depth sometimes is, especially on houses that sit far back from the street with a long front lawn. A deep front setback uses up depth before the addition even starts.
Height and wall heights for two storeys
A one-storey addition behind a bungalow rarely has height problems. A two-storey addition behind a backsplit is different, because main wall height and overall height are measured from established grade. On a sloped ravine lot, that grade can work against you at the rear.
On a sixty-year-old Etobicoke lot, the rear yard is rarely the problem. The problem is the sunroom somebody built in 1984 that already used your coverage.
When Etobicoke Creek Brings TRCA Into Your Project
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
Markland Wood's western edge runs along the Etobicoke Creek valley, and the golf course and parkland follow the creek. Parts of M9B sit near Mimico Creek and its tributary valleys. If your lot backs onto a valley, slopes down into one, or is anywhere near a watercourse, it may be inside TRCA's regulated area under the Conservation Authorities Act and Ontario Regulation 41/24. Check TRCA's online regulation mapping before you design anything. The regulated area often reaches into back yards well beyond the visible top of the slope.
Under the Ontario Building Code, a TRCA permit is applicable law. In practice, Toronto Building's zoning review flags the property, and the building permit sits on hold until a TRCA permit or clearance is on file. That's the most common reason a straightforward rear addition in Markland Wood stalls: the owner applied to the City first and found out about TRCA months later.
TRCA reviews these applications for erosion and slope stability, flooding, and the natural features of the valley. On a valley lot, expect them to ask for the top of bank to be staked with their staff on site and then surveyed. Their policies generally look for development to stay back from the long-term stable top of slope, plus a buffer. If the addition pushes toward the slope, you may need a geotechnical slope stability report. Sometimes the answer is that the addition has to be shorter, or go up instead of out.
Trees come next. Lots that fall under Toronto's Ravine and Natural Feature Protection By-law need a permit to injure or remove trees of any size in the protected area. On other lots, the private tree by-law covers larger trees. The mature oaks and maples behind many Markland Wood houses often sit right where the new foundation would go, and the arborist report and tree protection plan become part of the package.
When the Committee of Adjustment Gets Involved
If your design exceeds lot coverage, building depth, rear yard setback or any other zoning standard, the zoning examiner will list the deficiencies. You then apply for a minor variance to the Committee of Adjustment, Etobicoke York panel. The Committee applies the four tests in section 45 of the Planning Act. The variance has to be minor, desirable for the appropriate use of the land, and in keeping with the general intent of both the Official Plan and the zoning by-law.
For a rear addition, neighbours mostly object to three things: how close it comes to their yard, how a tall rear wall shades their patio, and whether it's a step toward something bigger. A modest coverage variance for a one-storey family room is usually far easier than a two-storey box running deep into the yard. If the lot is in TRCA's regulated area, the Committee circulates the application to TRCA for comment. TRCA can ask for conditions or a deferral, so it helps to have spoken to them before the hearing.
The Committee adds months, not weeks, because of the notice period, the hearing and the appeal window after the decision. Confirm current timelines with the City when you apply, since they change with caseload.
The Order That Keeps a Creek Lot Addition Moving
When a project needs both TRCA and the Committee, the order matters. Here's the sequence that has worked best for us on Etobicoke valley lots:
- Survey the lot, including topography, and stake the top of bank with TRCA staff if the lot is regulated.
- Draft a concept design and run a zoning check against 569-2013 and any site exceptions, so you know your variances before you commit.
- Pre-consult with TRCA on the concept. Their feedback on setbacks from the slope can change the footprint, and you only want to file variances once.
- File the Committee of Adjustment application with the final footprint, including the arborist report if trees are affected.
- Apply to TRCA for the permit, using the approved variance drawings.
- Submit the building permit application with full architectural and structural drawings, then answer the examiner's comments.
Some owners try to run all of these at the same time to save calendar time. That can work, but when TRCA asks for the addition to move back from the slope, the variance drawings and the permit drawings both have to be redone. PermitsHub has prepared drawings and run TRCA and Committee files on Etobicoke lots from Markland Wood to the Humber, and on most of those projects the early TRCA conversation saved more time than running everything in parallel would have.
Backsplits, Walkouts and Shallow Footings: What Examiners Flag
Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.
Once zoning and TRCA are cleared, the building permit review gets into the house itself, and 1960s Etobicoke houses come with their own problems.
Backsplits have floor levels at half-storey offsets. A rear addition has to meet one of those levels, and the stairs between them have to meet current code for rise, run, headroom and guards. Examiners often send back drawings where the addition's floor lines up with the kitchen but the connection to the lower family room was left vague.
Walkout lots on the valley side need footings at proper frost depth on the low side, and the drawings need to show grading that moves water away from both the house and the slope. TRCA and the City's engineering staff both look at drainage on these lots.
The original foundations are often block walls on modest footings. A new addition foundation dug deeper than the existing footing can undermine it. You then need underpinning along the shared wall, or a structural detail showing how the old footing is protected. Plan examiners and inspectors both ask about this, and inspectors will stop work at the footing stage if the detail on site doesn't match the drawings. PermitsHub's structural and architectural drawings show that junction from the start, because it's the comment we see most often on Etobicoke additions.
Last, the energy side. A new addition has to meet current Ontario Building Code energy efficiency requirements for its own walls, roof and windows. Large glazed rear walls facing the ravine are what most owners want, and they're also what most often needs the energy compliance calculations reworked.
A Quick Test Before You Pay for Drawings
Before committing to a design, answer three questions. Does the TRCA map show any part of your lot as regulated? After subtracting every existing structure, how much coverage is left? And does the addition you want push the house past the building depth limit, measured from where your front wall actually sits? If the answers are no, a reasonable amount, and no, you're probably looking at a straight building permit. If any answer goes the other way, budget the time for TRCA, the Committee, or both, and design the addition around what those reviews will accept rather than what the yard looks like it can hold.
Do I Need a Permit?
What are you planning to build or renovate?
Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.