Ontario Regulation 41/24 and TRCA Permits: What Changed for Ravine Lots

Since April 2024, TRCA permits are issued under a single provincial regulation that replaced the old Regulation 166/06. The permit test is narrower, some wetland-adjacent land dropped out of review, and a short list of small works no longer needs a permit. Most ravine-lot additions still do, though.

By PermitsHub Team9 min read

Key Takeaways

  • Ontario Regulation 41/24 replaced TRCA's Regulation 166/06 on April 1, 2024, and TRCA can now only weigh natural hazards like flooding, erosion and unstable slopes, not pollution or conservation of land.
  • The regulated area around wetlands shrank to 30 metres for all wetlands, but ravine valleys and floodplains are still regulated, so most additions, new homes and pools on ravine lots still need a TRCA permit before Toronto Building will issue yours.
  • A short list of small works is now exempt, including small non-habitable accessory structures, but each exemption carries conditions that a lot of homeowners miss.
  • The new rules give TRCA 21 days to confirm an application is complete and 90 days to decide, so a complete first submission now protects your schedule more than it ever did.

Ravine Lots Under 41/24

Ontario Regulation 41/24 took effect on April 1, 2024 and replaced TRCA's old Regulation 166/06 with one provincial rulebook for every conservation authority. For a GTA homeowner, three things changed. TRCA can now only refuse or condition a permit on natural hazard grounds (flooding, erosion, unstable soil or bedrock). The regulated area around wetlands shrank to 30 metres. A short list of small works became exempt. What did not change: if you're building an addition, pool or new house in a ravine valley, floodplain or erosion hazard, you still need a TRCA permit, and Toronto Building still won't issue your building permit until you have it.

One provincial rulebook replaced TRCA's own regulation

Before April 2024, each of Ontario's 36 conservation authorities had its own regulation under section 28 of the Conservation Authorities Act. TRCA's was Ontario Regulation 166/06. The wording was similar from authority to authority, but each one had its own mapping habits, its own policies and its own reading of how far its powers went. Regulation 41/24 swept all of that into one document titled Prohibited Activities, Exemptions and Permits.

The basic structure is familiar. You still can't do development in a regulated area, interfere with a wetland, or straighten, change or divert a watercourse without permission. "Development" still has its broad statutory meaning: building or placing a structure, adding to one, changing a building in a way that increases its size or its number of dwelling units, site grading, and placing or removing fill. That last part catches people. Regrading a backyard on a ravine lot can need a TRCA permit even if nothing gets built.

The change in the number of dwelling units matters more than most owners expect. Adding a legal basement suite inside a house that sits in a floodplain can count as development under the Act, even with no change to the building's outside. We've seen basement suite permits in the lower Don and Humber areas held up on exactly that point.

The narrower test: what TRCA can no longer weigh

Under the old regulation, TRCA could consider whether a project would affect the control of flooding, erosion, dynamic beaches, pollution or the conservation of land. That last phrase was broad. In practice it let staff ask for things like larger buffers to protect a valley's natural features, restoration planting tied to ecological goals, and design changes that had more to do with habitat than with hazards.

Regulation 41/24 removed pollution and conservation of land from the permit test. Now TRCA asks two questions. Is the activity likely to affect the control of flooding, erosion, dynamic beaches or unstable soil or bedrock? And would it create conditions that, if a natural hazard happened, could put people's safety at risk or damage property? If the answer to both is no, the permit should issue. Conditions also have to tie back to those hazard concerns.

On real files, this shows up in the comments that come back. Requests framed around ecology and habitat are less common. Comments about slope stability, the location of the stable top of bank, flood elevations and access in a flood are just as detailed as before. If your project's weak spot was always the slope, the new test doesn't help you much.

The new test took away TRCA's ecology arguments, not its geotechnical ones. If your addition is pushing toward the top of bank, the conversation is exactly as hard as it was in 2023.

Wetland and watercourse changes that shrank some regulated areas

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

The biggest mapping change was around wetlands. Under 166/06, the area of interference around provincially significant wetlands and larger wetlands was 120 metres. Regulation 41/24 sets 30 metres for all wetlands. Some properties on the edges of the Oak Ridges Moraine, in parts of Vaughan and Richmond Hill, and around the Rouge in northeast Scarborough and Markham were regulated only because they fell inside one of those wider wetland bands. Many of those lots are now outside the regulated area entirely.

The definition of a watercourse also tightened. It now means a defined channel with a bed and banks or sides, in which water flows regularly or continuously. Some swales and shallow drainage depressions that TRCA used to treat as watercourses don't meet that wording. That matters most for owners near the headwaters of creeks in York Region and Peel, and much less for a classic Toronto ravine lot, where the creek at the bottom is obviously a watercourse.

One thing hasn't moved. The regulated area for river and stream valleys still runs to the stable top of slope plus an allowance (15 metres in the provincial text). The floodplain is still regulated. If your house backs onto the Don, Humber, Highland Creek, Etobicoke Creek or the Rouge valley walls, the wetland changes almost certainly don't take you out of TRCA's jurisdiction.

Why the online map isn't the final word

TRCA's regulation mapping is a screening tool. The text of the regulation is what legally decides whether your lot is regulated, and the stable top of slope is a physical feature that someone has to stake in the field. Maps produced before April 2024 may still show the old 120 metre wetland bands, and mapping updates lag behind. If the map shows your lot as regulated only because of a nearby wetland, ask TRCA to confirm before you budget for a full review.

Small works that no longer need a permit, and the conditions that trip people up

Regulation 41/24 lists activities that are exempt from needing a TRCA permit even inside a regulated area. These are low-risk works the province decided didn't justify a full application. The ones ravine homeowners ask about most:

  • A non-habitable accessory building or structure that's subordinate to the house, with a footprint of 15 square metres or less (think a garden shed, not a cabana with a washroom).
  • Maintenance and repair of existing driveways, walkways and similar surfaces without expanding them.
  • Certain like-for-like maintenance of existing structures that doesn't increase their size or footprint.
  • Specific rural and servicing works such as some well installations and agricultural drainage, which matter more on estate lots in King or Caledon than in the city.

Each exemption comes with conditions, and that's where owners get into trouble. Most don't apply if the work is inside a wetland or a watercourse, and some have extra limits tied to specific hazards. A shed that's exempt on flat tableland can be a different story at the edge of an eroding slope. Expanding a driveway is not the same as repairing one. A new deck or a pool is not on the exempt list, even though plenty of people assume it is.

Before you rely on an exemption, read the exact wording against your site plan, or ask TRCA to confirm in writing. On ravine lots, Toronto Building plan examiners routinely flag properties in a TRCA regulated area during the applicable law review. They'll want either a TRCA permit or written confirmation that one isn't needed. Telling them it's exempt without a letter usually costs you a revision cycle.

Ravine lot projects that still need a TRCA permit

Here's the honest list for a typical Toronto, Markham or Vaughan ravine property. If the work is inside the regulated area and it's one of these, plan on a TRCA permit running alongside your building permit:

  • Rear additions, second-storey additions that add new foundations, and any increase in building footprint.
  • New custom homes and teardown rebuilds, especially where the new house sits closer to the valley than the old one.
  • In-ground pools, retaining walls and large decks on the valley side of the house.
  • Regrading, fill placement or removal, and landscaping that changes drainage toward the slope.
  • Basement walkouts, underpinning and lowering a basement in a floodplain, and adding a dwelling unit in a flood-prone building.
  • Garden suites placed in the rear yard toward the valley.

For these projects, a typical TRCA submission still includes a site plan showing the staked top of bank and the regulated limits, a topographic survey, and often a slope stability study from a geotechnical engineer. Floodplain sites may also need a floodproofing approach that reflects the regulatory flood elevation. On ravine lots in Don Mills, the Bridle Path and the Guildwood bluffs area, PermitsHub has had TRCA comments turn almost entirely on whether the drawings and the staking survey show the same top of bank. Get those to agree before you submit.

The new timelines, and how to keep them working for you

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Alongside the new regulation, amendments to the Conservation Authorities Act brought in firmer deadlines for permit applications. TRCA has 21 days to tell you whether your application is complete. Once it's deemed complete, it has 90 days to make a decision. If TRCA says the application is incomplete and you disagree, you can ask for an administrative review. If no decision arrives within the 90 days, you can appeal to the Ontario Land Tribunal.

In practice, the clock rewards a complete first package. If the geotechnical report is missing or the survey doesn't show the staked top of bank, the 21 day completeness notice will say so, and the 90 days won't start. Pre-consultation with TRCA staff before you submit still helps on anything bigger than a minor addition. It tells you which studies they'll want so you aren't commissioning a slope study after the fact. PermitsHub coordinates the TRCA package and the building permit drawings together, so the site plan, sections and grading match across both submissions.

Keep the sequence in mind as well. A TRCA permit counts as applicable law under the Ontario Building Code, so Toronto Building and the York and Peel municipalities won't issue your building permit until TRCA has signed off. The two reviews can run in parallel. The building permit simply can't be released first.

What Regulation 41/24 did not touch

Getting clear of TRCA doesn't mean getting clear of everything. The City of Toronto's Ravine and Natural Feature Protection Bylaw is a municipal bylaw, separate from the Conservation Authorities Act, and the provincial change didn't narrow it. It covers tree removal, grading and dumping in mapped ravine areas, and many ravine lots that dropped out of TRCA's wetland bands were never affected by it in the first place. Private tree bylaws in Toronto, Vaughan, Markham and Oakville also still apply.

Zoning still applies too. Many ravine lots carry site-specific zoning, minimum setbacks from the valley, or lot coverage limits that a TRCA approval doesn't override. If your addition needs a minor variance, the Committee of Adjustment will usually circulate the application to TRCA for comment anyway. That means a valley-side project can face TRCA's review at the variance stage and again at the permit stage, so having the hazard limits settled early saves you from redesigning between the two.

The short version for ravine owners: the province took away some of TRCA's discretion and trimmed the edges of the regulated map, but the valley wall and the floodplain are still TRCA's business. Confirm whether your lot is regulated and which hazard applies before you design. Then check any exemption against its exact conditions.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Zoning & Bylaws

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT