Beams, Posts and Footings When You Open Up a Toronto Main Floor

Taking out a bearing wall is the easy part. The real work is giving the load a new path: a beam sized by an engineer, posts at each end that run continuously to the basement, and proper concrete footings under those posts instead of the old floor slab. Here is how that load path works in a typical Toronto house, and what the City expects to see on your drawings.

By PermitsHub Team10 min read

Key Takeaways

  • When you remove a main floor bearing wall, the load gathers at the two ends of the new beam, so each end needs a post that carries that point load continuously down to a proper footing.
  • In most older Toronto houses the centre bearing wall sits right over the basement beam, which helps, but that beam was designed for a spread-out load and usually cannot take a new concentrated point load without a new post and footing beneath it.
  • A flush beam hides inside the ceiling and gives you a clean open space, but it means cutting and hanging every joist and shoring both sides, while a dropped beam is simpler and cheaper to build but leaves a visible bulkhead.
  • Toronto Building expects engineer-sealed details for the beam, connections, posts, blocking through each floor and the new footings, and inspectors will check the footing excavation and framing against those details before anything gets covered.

Following the Load Down

To remove a load-bearing wall on a Toronto main floor, you need three things working together: a new beam sized by a structural engineer to carry the floor and anything above it, posts at each end of that beam, and a continuous load path from those posts down to new or verified concrete footings in the basement. The posts cannot stop on the subfloor, and they cannot land on the existing basement slab. Each one has to bear on solid blocking through every floor it passes, then on a properly sized footing. Add temporary shoring during the work and engineer-stamped details on your permit drawings, and you have the full picture.

That sounds simple on paper. In practice, the beam is the part everyone talks about and the footings are the part that causes the delays. Here is the load path from the top down, the way a plan examiner and an inspector will look at it.

Why a Wall Turns Into Two Point Loads

A bearing wall spreads load evenly along its full length. The floor joists above sit on its top plate every 400 millimetres or so, and the wall passes that load straight down in a continuous line. Remove the wall and put in a beam, and the beam collects all of that load and delivers it to just two places: its ends. Everything the wall used to share along four or five metres now arrives at two small bearing points.

That's the whole reason for the posts and footings. A wall resting on the basement beam was fine. A concentrated point load from a beam carrying the second floor, part of the roof and maybe a bearing wall upstairs is a different animal. The engineer's job is to calculate how big that point load is and then prove every piece below it can take it.

The Typical Toronto Layout: Centre Wall Over a Basement Beam

Most detached houses and semis built in Toronto from the early 1900s through the post-war years share the same basic structure. Joists span from the front and rear exterior walls to a line down the middle of the house. On the main floor that line is the centre bearing wall, often the one between the living room and dining room, or the hallway wall beside the stairs. In the basement, directly below it, sits a beam: a built-up wood beam in older houses, a steel I-beam in many post-war bungalows, resting on posts, brick piers or adjustable steel columns.

Because the main floor wall lines up with the basement beam, the load path is already partly there. But that basement beam was designed to carry the evenly spread load of a wall above it, with its own supports spaced for that loading. When your new main floor beam drops its end load onto one spot of the old basement beam, that spot may fall between the existing supports. Old wood beams in particular are often undersized by current standards, notched for ductwork, or sitting on piers that have settled.

The basement beam lining up under your wall is good news, not a free pass. It was built to carry a line of load, and you are about to hand it two heavy points.

The usual fix is a new post placed directly under each end of the main floor beam, running down past or through the basement beam to its own footing. Sometimes the engineer reinforces or replaces the basement beam as well. On the Leslieville and Danforth semis we draw for, the basement beam is frequently an old timber member that has been notched or drilled over the decades, and the engineer ends up treating it as decoration rather than support.

Flush Beam or Dropped Beam: What Changes on Site

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

This is the decision homeowners care about most, because it decides what the ceiling looks like. It also changes how much structural work happens.

Dropped beam

A dropped beam hangs below the ceiling. The existing joists simply rest on top of it, the same way they rested on the wall. It's quicker to install, needs less disruption to the floor above, and is usually the lower-cost option. The trade-off is a visible bulkhead across the room, often somewhere between a hand's width and a foot deep depending on span and material. In a house with tall ceilings that's barely noticed. In a bungalow with low main floor ceilings it can feel heavy.

Flush beam

A flush beam sits up inside the joist depth so the ceiling stays flat. To get it there, the crew cuts every joist crossing the beam line and reconnects each one to the side of the beam with metal joist hangers. With steel, that typically means bolting wood nailers into the beam's web so the hangers have something to fasten to. Because the joists are cut, both sides of the floor have to be shored while the work happens. Flush beams are often deeper or heavier than a dropped beam for the same span, since they have less room to work with. Expect more labour, more inspection detail and more chance of surprises once the ceiling is open.

Neither choice changes the posts and footings below. The point loads still have to go to the ground either way.

Posts: Following the Load All the Way Down

The post is where most of the field mistakes happen. A beam end bearing on a stack of studs that stops at the subfloor is not a load path. The load has to pass through every layer between the beam and the footing without crushing anything soft along the way.

  • At the beam: a built-up stud post or steel column sized by the engineer, with a defined bearing length under the beam and a connection that keeps the beam from sliding off.
  • Through the main floor: solid blocking (sometimes called squash blocks) between the joists directly under the post, so the load does not crush the subfloor or the rim of a joist.
  • Across the basement ceiling: either a new post under that blocking, or bearing onto a basement beam the engineer has confirmed can take the point load.
  • At the bottom: a steel or wood post sitting on a new concrete pad footing, with a base plate or connection detail shown on the drawings.

If there's a bearing wall on the second floor above the one you're removing, the engineer will also look at whether it carries roof load down onto your new beam. Sometimes there's an upstairs post or heavy wall sitting right on the line, and that changes the beam size and the point load dramatically. This is why we ask for photos of the second floor and attic, not just the room being opened up.

Semi-detached houses add one more wrinkle. Often one end of the beam lands on the party wall, which means pocketing into shared brick and confirming that wall can take the load. That is its own conversation, and it can involve your neighbour.

Footings: Why the Basement Slab Doesn't Count

The most common thing we see sent back, or flagged in the field, is a new post sitting on the existing basement floor. In older Toronto houses that slab is thin, usually unreinforced, often poured long after the house was built, and sometimes cracked or sloping. It was never meant to carry a concentrated load. Put a heavy point load on it and the post can punch through or settle, and the floors above start to sag and crack the plaster.

So the slab is cut out where each new post goes, the soil is excavated, and a new concrete pad footing is poured. The size and depth come from the engineer's calculation of the load and the soil's bearing capacity. The Ontario Building Code sets minimum footing areas for columns based on how many floors they support, but on a wall removal the engineer usually designs to the actual load rather than leaning on the table minimum. Footings are commonly reinforced and must sit on undisturbed soil, not fill.

A few real-world snags come up again and again in Toronto basements:

  • The post location lands on the main heating trunk line or a drain line running beside the old basement beam, so ductwork or plumbing has to move before the footing goes in.
  • Digging hits soft fill or water, especially in houses near old ravines and creek beds, and the engineer has to revisit the footing depth.
  • The owner plans to lower or underpin the basement in a few years, and a footing poured at today's floor level ends up too high. Tell your designer about future basement plans now.
  • An existing pier turns out to be loose brick sitting on nothing in particular, and it gets replaced rather than reused.

Temporary Shoring While the Wall Comes Out

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Between the moment the wall is removed and the moment the new beam is carrying load, something has to hold up the house. That's temporary shoring: a stud wall or a row of adjustable posts with a header, set up close to the wall being removed. For a dropped beam, one shoring line on one side may be enough. For a flush beam where joists are being cut, you need shoring on both sides because the joists on each side become independent spans until they're hung.

Here's the part people miss: the shoring load goes somewhere too. If the temporary posts on the main floor sit on the subfloor, the basement ceiling below needs its own temporary support lined up under them, bearing on timbers that spread the load across the slab. Contractors who shore only the main floor sometimes see the floor deflect and plaster crack upstairs before the beam is even in. On bigger spans, or where a flush steel beam has to be lifted in, the engineer may note a shoring sequence on the drawings.

What Toronto Building Expects on the Drawings

Removing a bearing wall needs a building permit in Toronto, and the drawings must show the structural work clearly enough for an examiner to follow the load from the roof down to the soil. Beam design falls outside the prescriptive Part 9 tables in most open-concept cases, so the structural portion is typically designed and sealed by a professional engineer. Expect the examiner to look for:

  • A floor plan showing the wall being removed, the new beam location, and the posts at each end.
  • Beam size and material (steel section, LVL or engineered lumber), with span and whether it's flush or dropped.
  • Connection details: beam to post, joist hangers for flush beams, bolts, bearing plates and pockets into masonry where applicable.
  • A basement plan showing each new post and footing, with footing dimensions, depth and reinforcement.
  • Sections or details showing the blocking through each floor so the load path is continuous.
  • Engineer's seal on the structural sheets, and in some cases a commitment for the engineer to review the work on site.

Vague notes like "beam by others" or "post to footing as required" are a reliable way to get a revision request. The examiner wants sizes and details on the page. When PermitsHub prepares wall removal drawings, we coordinate the engineer's design onto the architectural set so the beam, posts and footings line up on every sheet, which avoids the back-and-forth that comes from mismatched plans.

On site, the inspector will want to see the footing excavation before concrete goes in, then the beam, posts, hangers and blocking before drywall closes it up. Keep the stamped drawings on site. Inspectors compare what's installed against the details, and substitutions (a different beam, a smaller post, skipped blocking) without the engineer's sign-off can stall the job until a revised detail comes back. If you'd like a second set of eyes before you commit, PermitsHub can review your floor plan and photos and tell you where the load path is likely to need the most work.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

Structural

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT