PermitsHubPermitsHub

By Area

Lowering a Basement in Lawrence Manor or Glencairn (M6A, M6B)

Most postwar bungalows in Lawrence Manor and Glencairn have basements that are too shallow for a legal suite, and lowering them is a structural project. You will need a building permit, stamped underpinning drawings and new drainage, and the old rear addition is often the trickiest part. Here is what the North York office looks for and where these jobs usually stall.

By PermitsHub Team9 min read

Key Takeaways

  • Lowering a basement in an M6A or M6B bungalow needs a Toronto building permit with stamped structural drawings that show the underpinning sequence, new footing depths and how the work ties into any existing addition.
  • Rear family rooms and enclosed porches added in the 1960s and 70s often sit on their own shallow footings or a crawlspace, so the engineer has to detail that junction or the addition can settle when the main basement is dug out.
  • Dropping the floor puts it below the original weeping tile, which means a new interior drainage layer, a sump pit and a backwater valve, and you should confirm the street sewer depth before deciding how far down to go.
  • If the lowered basement is meant to become a secondary suite, file the suite and the structural work together so the ceiling heights, egress windows, fire separation and plumbing are reviewed as one package.

Digging Down in M6A

To underpin and lower a basement in a Lawrence Manor or Glencairn bungalow, you need a City of Toronto building permit reviewed by the North York district office, structural drawings stamped by a professional engineer that show the underpinning or benching method and the excavation sequence, and new drainage: an interior perimeter drain, a sump pit with discharge to grade, and a backwater valve on the main drain. If the lowered space is going to be a secondary suite, the suite is usually filed in the same application so ceiling height, egress, fire separation and plumbing are all reviewed together. Electrical work goes through the ESA separately.

That is the short version. The longer version depends on what your particular house is sitting on, what a previous owner added out back, and how deep your sewer is. Those three things decide whether the job is straightforward or turns into a series of revisions.

What M6A and M6B Bungalows Are Actually Sitting On

The streets between Bathurst and the Allen, north and south of Lawrence, were mostly built out in the late 1940s and 1950s. The typical original house is a one storey brick bungalow, sometimes a side split, with a basement that was built for a furnace, a laundry tub and storage. Clear height in those basements often sits somewhere around six feet under the joists, and less under the main beam and ductwork. That is not enough for a legal living space, so lowering the floor is the only way to get there.

The footings under these houses are usually shallow and narrow by current standards. Foundation walls are a mix of poured concrete and concrete block, and you will sometimes find both on the same house where a wall was rebuilt. Block walls matter because they behave differently when you dig beneath them, and the engineer needs to know which one you have before designing the pins. Soils in much of the area are clay, which holds its shape well during excavation but can trap water in pockets, so the crew may hit damp conditions on one side of the house and bone dry soil on the other.

Lots here are generally detached with narrow side yards. That puts your excavation close to the neighbour's foundation, which is the first thing a careful engineer thinks about and the first thing a nervous neighbour asks about.

The Rear Addition Problem Nobody Budgets For

A large share of the bungalows we see in Lawrence Manor and Glencairn have a rear family room, a sunroom or an enclosed porch that went on decades after the original house. Those additions were rarely built on a full basement. More often they sit on a shallow strip footing, a crawlspace or a slab, and the footing is not connected to the original foundation in any meaningful structural way.

When you lower the main basement, the wall that separates the original house from the addition is now holding back soil that supports the addition's floor and footing. If that junction is not designed, you can get cracking, a sloping family room floor or worse. Plan examiners in the North York office will flag drawings that show the underpinning stopping at the old rear wall with no note about what happens on the other side.

The original house is rarely the problem. It's the family room someone added in 1972 on a footing two feet deep that decides how the underpinning gets designed.

There are a few common ways engineers handle it, and the right one depends on what is found when the area is opened up:

  • Underpin the shared wall and the addition's own footings so the whole structure bears at the new depth.
  • Step the new footing up at the junction and design a retaining condition so the addition's soil stays where it is.
  • Leave a bench or ledge along that one wall while fully underpinning the rest, accepting some lost floor area.
  • In rare cases, take down and rebuild a poorly built addition rather than pay to support it.

If you don't know what the addition sits on, a small test pit or opening an existing crawlspace before the drawings are finalized saves a revision later. Guessing and fixing it during construction usually means a field change, an engineer's site visit and sometimes a revised permit drawing.

Underpinning or Benching: Choose the Method Before the Drawings

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Underpinning means excavating below the existing footing in short segments and pouring new concrete beneath it so the wall bears at the new depth. You keep the full floor area. Benching (often called a bench footing) leaves the existing footing alone and pours a concrete ledge along the inside of the wall, sloped down to the new floor level. It is less invasive and usually costs meaningfully less, but you lose floor width around the perimeter, which can make a suite layout tight in a bungalow that was small to begin with.

For underpinning, the structural drawings have to show the sequence. Pins are dug in segments, typically labelled in a repeating pattern, and no two adjacent segments are open at the same time. The engineer sets segment width, footing size, the new depth, dowelling and any requirements for the block walls above. Toronto Building expects the engineer to review the work in the field and provide a letter confirming general conformance, and inspectors will ask for those reports, so line them up with the contractor from the start.

Protecting the neighbour

The City does not require your neighbour's consent to underpin your own walls, but a lowered footing near a side lot line can affect their foundation if it is shallower than yours ends up being. Good practice is a pre-construction photo survey of the neighbouring house, a friendly conversation before the excavator shows up, and an engineer who has looked at how close the two foundations really are. A neighbour who sees a crack and has no baseline photos will assume you caused it.

Drainage: Backwater Valve, Sump Pit and the Sewer Depth Question

Once the floor goes down, it is below the original weeping tile, which was laid around the outside of the old footing. That tile is now too high to protect the new floor. The standard fix is an interior perimeter drain under the new slab, connected to a sump pit, with a pump that discharges to the surface away from the house. Toronto's sewer rules do not allow foundation drainage to go into the sanitary sewer, so the drawings need to show where the sump discharges and the inspector will check it.

Because you are adding fixtures below grade, a backwater valve on the main building drain is expected. It is also what makes you eligible for the City's Basement Flooding Protection Subsidy Program, which only applies to work done under a permit. The subsidy terms, caps and paperwork change over time, so confirm the current details with the City before you count on it.

Here is the question people skip: how deep is the sewer at the street? Older laterals in this area were set for a basement floor drain at the original depth. If you lower the floor enough that new fixtures sit below the level where sewage can flow out by gravity, you need a sewage ejector pump, which adds cost, noise and maintenance. A camera inspection of the lateral answers this and also tells you whether the old clay pipe has been invaded by roots from the mature trees these streets are known for. If the lateral needs replacing, now is the time, while the floor is open.

What the North York District Office Wants in the Package

Underpinning applications for properties in M6A and M6B are reviewed out of the North York district office. A complete submission typically includes:

  • Existing and proposed basement floor plans with dimensions and the new floor elevation.
  • Building sections showing the existing footing, new footing depth, slab build up, insulation and finished ceiling heights.
  • Sealed structural drawings for the underpinning or benching, including the excavation sequence and any work at an existing addition.
  • Plumbing layout showing new fixtures, the backwater valve, sump pit and discharge location.
  • If a suite is included: fire separations, smoke alarm and CO alarm locations, egress windows, HVAC approach and the second entrance.

The provincial review clock for houses is short on paper, but it restarts every time you resubmit after comments. The usual causes of a comment letter are missing sections through the addition, ceiling heights that do not work under the beam once the ducts are drawn in, and a sump discharge shown pointing at the side lot line. PermitsHub prepares the architectural and coordination drawings, works with the structural engineer on the pin sequence, and answers examiner comments so the file does not sit in limbo between rounds.

Have a project in mind? Get an honest, no-pressure permit review from PermitsHub.

Most owners in Lawrence Manor and Glencairn are not lowering the basement just for a taller rec room. They want a rental suite or a space for family. The Ontario Building Code sets minimum ceiling heights for suites in existing houses, with a slightly lower allowance under beams and ducts. Confirm the exact figures against the current code with your designer, and remember that the number that matters is the finished height after flooring, insulation and drywall, not the height of the bare slab.

The suite also needs a separate entrance. In a bungalow with a narrow side yard, a new below-grade stairwell can run into zoning limits on how far it projects and how close it gets to the lot line, which can push you to the Committee of Adjustment. A rear entrance is often easier if the yard allows it. Egress windows need clear openings at the new floor level, which often means enlarging window wells, and that excavation should be coordinated with the underpinning so you are not digging the same wall twice.

Inspections and the Order They Happen In

Sequence matters on a lowering job because each stage gets buried by the next one. A typical order looks like this: the engineer reviews pin excavations and reinforcement before each pour, the City inspects the underpinning as it progresses or relies on the engineer's reports, under-slab plumbing and drainage are inspected before the slab goes in, then framing, insulation, fire separation and final. ESA inspects the electrical on its own schedule.

The most expensive mistake is pouring the slab before the under-slab plumbing inspection. If that happens, the inspector can ask you to break it open. Book inspections early, keep the engineer's field reports in one place on site, and make sure the contractor knows that the approved drawings, not their usual way of doing things, are what the inspector is checking against. On the jobs we have run in these two neighbourhoods, the ones that close cleanly are the ones where the addition, the sewer depth and the suite layout were all settled before the first pin was dug.

Do I Need a Permit?

1
›
2
›
3
›
4

What are you planning to build or renovate?

Ready to move forward? PermitsHub handles permit drawings, submission, and revisions - flat-rate, GTA-wide.

Related Reading

More in this category

By Area

FAQ

Related questions

Get started

Tell us about your project.

Free, no-pressure quote within one business day.

● Flat-rate quotes - no surprise fees

● Revisions included until approval

● Most enquiries responded to same day

Free Home Permit QuoteNo commitment · 30 sec
1
2
3

What are you building?

SCROLL TO SEE ALL 20 PERMIT TYPES

Prefer to call? 647-961-4070
CALL NOWFree Home Permit Quote30 SECONDS - NO COMMITMENT